HB 491-ALASKA RAILROAD REVENUE BONDS 1:56:05 PM CO-CHAIR GATTO announced that the final order of business would be HB 491, "An Act authorizing the Alaska Railroad Corporation to issue revenue bonds to finance rail transportation projects that qualify for federal financial participation; and providing for an effective date." PAT GAMBLE, President and Chief Executive Officer, Alaska Railroad Corporation, said state railroad transfer statute requires the approval of the legislature for selling bonds. The bill is a package for bond approval, he explained. 1:57:30 PM CO-CHAIR GATTO asked what the bonds will be used for. MR. GAMBLE said the bill is to accelerate an effort that began in 1996 to recapitalize the Alaska Railroad infrastructure, which is the main track. Over the last ten years there has been a work program to incrementally improve the main line, and now a mechanism through SAFETEA-LU [Safe, Accountable, Flexible, Efficient Transportation Equity Act: A Legacy for Users] allows the improvements to be accelerated with the use of bonding. CO-CHAIR GATTO asked if wooden ties are being replaced with concrete ties. MR. GAMBLE said yes, where needed. He said these are capital grant receipt revenue bonds in aggregate not to exceed $165 million. The project is to rehabilitate substandard or potentially unsafe tracks, which is the railroad's core work effort using federal dollars since 1996. He said, "We began receiving federal railroad administration dollars through appropriations from Senator Stevens, and we went on to the federal formula fund process...because we move passengers on a regularly-scheduled year-round basis." He said the entitlement has increased over the years, and between those and net earnings, "we have put this money in a very concerted way into that mainline track." He added that about $220 million have been put "into that one specific area...primarily from Anchorage to Fairbanks, but, secondarily, from Seward to Anchorage." 2:00:20 PM MR. GAMBLE showed a graph of the derailments between 1996 and 2005, which is primarily due to poor track condition. There are huge costs associated with derailments on the main track, but the trend is going in the right direction, he stated. The train accident rate is [decreasing] as a result of mainline investments. He said the money will allow the welding of rail and "the click clack will be gone" as well as the battering to the joints, which can cause dangerous breaks and derailments. 2:02:34 PM CO-CHAIR GATTO asked why the rail is not welded. MR. GAMBLE said the rails weren't welded until four years ago when an expert was hired who debunked the idea that rails could not be welded in cold climate conditions. REPRESENTATIVE NEUMAN asked if the need to haul freight for the gas line created this priority. PAT GAMBLE said that has been a goal of the Alaska railroad for the five years that he has been there. 2:04:23 PM CO-CHAIR GATTO said he thought wooden ties were better but was told concrete ties are more effective in preventing derailments. MR. GAMBLE said he is not proposing eliminating wooden ties; concrete ties are not needed everywhere, but they are a benefit on the curves where accidents occur. Concrete ties and welded rails provide stability preventing the flux that causes wheels to pop off. Wooden ties will be replaced cyclically, he said. 2:07:11 PM MR. GAMBLE said there are 3,200 ties per mile. The project also includes replacing river rock with granite ballast for a more stable roadbed. He said gas pipe will be heavy-620 pounds per foot, so "we're moving up to 140-pound rail." There will also be a collision avoidance program to reduce human error, he said. CO-CHAIR GATTO said the size of the pipe in unknown, but he asked if the heaviest pipe will be heavier than a load like rocks, for example. MR. GAMBLE said he is predicting the size of the pipe, and the track will be capable of handling a least one piece. 2:10:17 PM MR. GAMBLE said bonding will allow for faster improvements. He said 300,000 carloads of hazardous material traverse "some pretty sacred country," so he believes the public would demand this work. This debt "actually creates a financing structure that puts some real rigor and discipline into our capital program." The program will not vary each year as it has because of the percentage of revenue going to paying the debt service. 2:12:34 PM REPRESENTATIVE NEUMAN said a Wasilla realignment project has been discussed, and he asked if any of those funds are included. The people in Wasilla want the track moved west to go around town, and he said it is an excellent way to get it near Pt. McKenzie for coal shipping. MR. GAMBLE said the Knik Bridge is not part of this funding. REPRESENTATIVE NEUMAN asked for clarity of costs for track upgrades and if some of that money could be used for a spur. 2:15:07 PM MR. GAMBLE said the track realignment between Anchorage and Wasilla has been done. The Wasilla bypass will take up to $200 million and the route is still being chosen. A feasibility study is underway, and for the last four years there has been no consensus. Prices of land in that area are going up and the railroad is running out of options, he noted. Engineering solutions may need to be employed that don't move the railroad outside of Wasilla but raises it over the roads. Representative Don Young told him he supports putting the railroad on the [proposed Knik] bridge even though it is unaffordable. Senator Ted Stevens would like to see the rail go across the bridge, he said, and the railroad is looking at that possibility. 2:18:41 PM REPRESENTATIVE THOMAS said people create a community around the railroad and now they don't want the railroad nearby. CO-CHAIR ELKINS asked if the [proposed Knik] bridge has to built to handle the railroad now. MR. GAMBLE opined that now is the time to do the planning. CO-CHAIR GATTO noted that there is very little room for cars at the Wasilla depot, and the population is out of control. One thought is to elevate the track, which is right in front of a condominium, but he asked about tunneling instead. MR. GAMBLE said it can be done, depending on the soil and water. 2:20:50 PM CO-CHAIR GATTO said it is only one intersection that is such a problem in Wasilla. MR. GAMBLE said there are water table problems so it can't go underground. If all the freight went across the [proposed] bridge, then Wasilla would only have the less frequent passenger trains, which may solve the problem. CO-CHAIR GATTO said the gas line is at least six years away, "and I can't imagine what that intersection will look like." 2:23:14 PM MR. GAMBLE said the railroad will continue the feasibility study of that intersection, but surmised it will take "an ugly scene at that crossing to trigger some action." It is a city problem and a borough solution, and things are stymied. He said SAFETEA-LU allowed the railroad a 6-fold increase in federal entitlements. The federal funds are guaranteed in perpetuity, so the full faith in credit of the Alaska Railroad is not at risk. He said the railroad will spend that money, "whether we spend it on debt service or whether we spend it incrementally over a extended period of time." The cost of materials are going up, so the purchases can be made in bulk and stored. He said passenger service is increasing, requiring the line to be safe and smooth. There will be no impact to other capital programs, he stated. 2:26:30 PM REPRESENTATIVE THOMAS said, so this won't extend the railroad? MR. GAMBLE said no. CO-CHAIR GATTO asked the distance to any Canadian rail line. MR. GAMBLE said it is about 1,000 miles to their railroad. 2:27:09 PM MR. GAMBLE said the proposed financing is up to $165 million, with three bond sales over the next six years. Each would have to be approved by the railroad board of directors. The year with the largest debt service would be 49 percent of available funds. He said if Senator Ted Stevens gives the railroad another earmark, "we would see the need for that $165 million to come down to a lower number; the debt service would reflect that." He sees no event that would have the railroad coming back to the legislature for more money. CO-CHAIR GATTO said the Europeans have been using welded railroads since he learned how to walk, and they have bullet trains. He predicted a savings for using welded railroads. 2:30:52 PM MR. GAMBLE said the railroad workers are local, "and there's a momentum there...that is not refreshed from the outside." There was a resistance to going to welded rails. Now there are experienced outside workers with a host of new ideas, he said. CO-CHAIR ELKINS asked if the rails are longer when welded. MR. GAMBLE said yes; they are built to half-mile lengths, and the curve is put into it. The concrete tie holds it. The acuteness of the curves has been reduced, he added. Therefore the average velocity has gone up steadily. 2:34:45 PM MR. GAMBLE said the railroad gets very little homeland security money. It all goes to the state, he noted. REPRESENTATIVE NEUMAN referred to the mainline density history and the million gross tons from Portage to Anchorage and to Matanuska-Susitna. He asked if that would change if there was a line to Pt. Mackenzie, "assuming that we would be doing coal down through there." He asked about the economic development opportunities. 2:37:36 PM MR. GAMBLE said he can provide that information. REPRESENTATIVE THOMAS moved to report HB 491 out of committee with individual recommendations and with no accompanying fiscal notes. There being no objection, HB 491 was reported out of the House Transportation Standing Committee.