Note: the audio and video recordings are distinct records and are obtained from different sources. As such there may be key differences between the two. The audio recordings are captured by our records offices as the official record of the meeting and will have more accurate timestamps. Use the icons to switch between them.

Download Mp3. <- Right click and save file as

Audio Topic
01:21:18 PM Start
01:21:56 PM Presentation: Alaska Marine Highway System
02:27:32 PM Adjourn
* first hearing in first committee of referral
+ teleconferenced
= bill was previously heard/scheduled
-- Please Note Time --
+ Alaska Marine Highway System TELECONFERENCED
+ Bills Previously Heard/Scheduled TELECONFERENCED
                 SENATE FINANCE COMMITTEE                                                                                       
                      April 10, 2019                                                                                            
                         1:21 p.m.                                                                                              
                                                                                                                                
                                                                                                                                
1:21:18 PM                                                                                                                    
                                                                                                                                
CALL TO ORDER                                                                                                                 
                                                                                                                                
Co-Chair  Stedman   called  the  Senate   Finance  Committee                                                                    
meeting to order at 1:21 p.m.                                                                                                   
                                                                                                                                
MEMBERS PRESENT                                                                                                               
                                                                                                                                
Senator Natasha von Imhof, Co-Chair                                                                                             
Senator Bert Stedman, Co-Chair                                                                                                  
Senator Click Bishop                                                                                                            
Senator Peter Micciche                                                                                                          
Senator Donny Olson                                                                                                             
Senator Mike Shower                                                                                                             
Senator Bill Wielechowski                                                                                                       
Senator David Wilson                                                                                                            
                                                                                                                                
MEMBERS ABSENT                                                                                                                
                                                                                                                                
Senator Lyman Hoffman                                                                                                           
                                                                                                                                
ALSO PRESENT                                                                                                                  
                                                                                                                                
Mary    Siroky,   Deputy    Commissioner,   Department    of                                                                    
Transportation and  Public Facilities; Matt  McLaren, Alaska                                                                    
Marine Highway Business  Enterprise and Development Manager,                                                                    
Department of Transportation and Public Facilities.                                                                             
                                                                                                                                
SUMMARY                                                                                                                       
                                                                                                                                
PRESENTATION: ALASKA MARINE HIGHWAY SYSTEM                                                                                      
                                                                                                                                
                                                                                                                                
^PRESENTATION: ALASKA MARINE HIGHWAY SYSTEM                                                                                   
                                                                                                                                
1:21:56 PM                                                                                                                    
                                                                                                                                
Co-Chair  Stedman  informed  that the  committee  discussion                                                                    
would include a discussion of  that the AMHS would look like                                                                    
if it  operated from October  1 through  June 1 of  the next                                                                    
fiscal  year.  He  noted  that  the  governor  had  proposed                                                                    
cutting service during that time.                                                                                               
                                                                                                                                
1:23:37 PM                                                                                                                    
                                                                                                                                
MARY    SIROKY,   DEPUTY    COMMISSIONER,   DEPARTMENT    OF                                                                    
TRANSPORTATION AND PUBLIC  FACILITIES, thanked the committee                                                                    
for  the opportunity  to  have  in-depth conversations  with                                                                    
committee members over previous weeks.                                                                                          
                                                                                                                                
MATT MCLAREN, ALASKA MARINE  HIGHWAY BUSINESS ENTERPRISE AND                                                                    
DEVELOPMENT  MANAGER,   DEPARTMENT  OF   TRANSPORTATION  AND                                                                    
PUBLIC FACILITIES, introduced himself.                                                                                          
                                                                                                                                
1:24:05 PM                                                                                                                    
                                                                                                                                
Mr.  McLaren  discussed  the  presentation,  "Alaska  Marine                                                                    
Highway System (AMHS) Overview" (copy on file).                                                                                 
                                                                                                                                
Mr. McLaren turned to Slide 2, "AMHS Ports of Call":                                                                            
                                                                                                                                
      33 Alaskan Communities, Prince Rupert, & Bellingham                                                                       
                                                                                                                                
Mr. McLaren noted that the map  on the page showed the ports                                                                    
served by AMHS.                                                                                                                 
                                                                                                                                
1:24:38 PM                                                                                                                    
                                                                                                                                
Mr.  McLaren  displayed  Slide  3,  "AMHS  Port  and  Vessel                                                                    
Codes":                                                                                                                         
                                                                                                                                
     Communities                                                                                                              
     ANB = Metlakatla (Annette Bay)                                                                                             
     AKU = Akutan                                                                                                               
     ANG = Angoon                                                                                                               
     BEL = Bellingham, WA                                                                                                       
     CBY = Cold Bay                                                                                                             
     CDV = Cordova                                                                                                              
     CHB = Chenega Bay                                                                                                          
     CHG = Chignik                                                                                                              
     FPS = False Pass                                                                                                           
     GUS = Gustavus                                                                                                             
     HNS = Haines                                                                                                               
     HNH = Hoonah                                                                                                               
     HOM = Homer                                                                                                                
     JNU = Juneau (Auke Bay)                                                                                                    
     KAE = Kake                                                                                                                 
     KCV = King Cove                                                                                                            
     KOD = Kodiak                                                                                                               
     KTN = Ketchikan Communities                                                                                                
     OLD = Old Harbor                                                                                                           
     ORI = Port Lions                                                                                                           
     OUZ = Ouzinkie                                                                                                             
     PEL = Pelican                                                                                                              
     PSG = Petersburg                                                                                                           
     SDP = Sand Point                                                                                                           
     SDV = Seldovia                                                                                                             
     SGY = Skagway                                                                                                              
     SIT = Sitka                                                                                                                
     TAT = Tatitlek                                                                                                             
     TKE = Tenakee                                                                                                              
     UNA = Unalaska/Dutch Harbor                                                                                                
     VDZ = Valdez                                                                                                               
     WRG = Wrangell                                                                                                             
     WTR = Whittier                                                                                                             
     YAK = Yakutat                                                                                                              
     YPR = Prince Rupert, B                                                                                                     
                                                                                                                                
     Ships                                                                                                                    
     AUR M/V Aurora                                                                                                             
     CHE FVF Chenega                                                                                                            
     COL M/V Columbia                                                                                                           
     FWX FVF Fairweather                                                                                                        
     KEN M/V Kennicott                                                                                                          
     LEC M/V LeConte                                                                                                            
     LIT M/V Lituya                                                                                                             
     MAL M/V Malaspina                                                                                                          
     MAT M/V Matanuska                                                                                                          
     TUS M/V Tustumena                                                                                                          
     TAZ M/V Tazlina                                                                                                            
     M/V Motor Vessel                                                                                                           
     FVF Fast Vehicle Ferry                                                                                                     
                                                                                                                                
1:24:55 PM                                                                                                                    
                                                                                                                                
Mr.  McLaren referenced  Slide  4,  "Historical Revenue  and                                                                    
Operating Cost," which  showed a graph entitled  ' AMHS Fare                                                                    
Box  Recovery Rate  1987-2018.' The  dark blue  lines showed                                                                    
system operating costs, and the  salmon colored lines showed                                                                    
the revenue  generated. The  wavy line  showed the  fare box                                                                    
recovery rate, which was calculated  by dividing the revenue                                                                    
by the  total operating cost. The  high was in 1992,  with a                                                                    
fare box recovery rate of just over 60 percent.                                                                                 
                                                                                                                                
1:26:09 PM                                                                                                                    
                                                                                                                                
Co-Chair von Imhof observed that  operating costs had stayed                                                                    
consistent  from  1987   up  to  2005,  at   which  time  it                                                                    
increased. She asked what caused the increase in costs.                                                                         
                                                                                                                                
Mr.  McLaren stated  there were  a few  factors. He  relayed                                                                    
that in  2005-2006 3  new vessels were  added to  the fleet,                                                                    
contract negotiations  had resulted  in increased  cost, and                                                                    
some smaller coastal communities were added to the call.                                                                        
                                                                                                                                
1:27:12 PM                                                                                                                    
                                                                                                                                
Co-Chair  Stedman asked  whether  an agreement  to move  the                                                                    
salary/benefit level up  by 20 percent, as a  result of fast                                                                    
ferry work, had resulted in the cost increase.                                                                                  
                                                                                                                                
Mr.  McLaren thought  the wage  increases were  for 6  and 7                                                                    
percent. He offered to provide an exact number later.                                                                           
                                                                                                                                
1:27:54 PM                                                                                                                    
                                                                                                                                
Senator  Wilson asked  for a  list of  vessel ages  and port                                                                    
acquisition dates.                                                                                                              
                                                                                                                                
Mr. McLaren agreed to provide the information.                                                                                  
                                                                                                                                
1:28:36 PM                                                                                                                    
                                                                                                                                
Mr. McLaren  highlighted Slide 5, "Economic  Impacts," which                                                                    
showed two charts depicting the  number of AMHS trips by the                                                                    
top  ten community  of residence  in 2014;  and the  top ten                                                                    
destinations of AMHS summer visitors  from 2011. He informed                                                                    
that  the data  on the  slide was  provided by  the McDowell                                                                    
Group in January 2016.                                                                                                          
                                                                                                                                
1:29:48 PM                                                                                                                    
                                                                                                                                
Senator  Micciche  wanted  to   make  a  connection  between                                                                    
bookings and economic impact. He  asked about the use of two                                                                    
different years.                                                                                                                
                                                                                                                                
Mr. McLaren offered to provide more detail later.                                                                               
                                                                                                                                
Ms. Siroky stated that the purpose  of the slide was to give                                                                    
an  idea  of  where  people  were getting  on  and  off  the                                                                    
vessels.                                                                                                                        
Co-Chair  Stedman asked  whether Anchorage  was a  port that                                                                    
the Alaska Marine Highway System (AMHS) stopped in.                                                                             
                                                                                                                                
Ms.  Siroky  replied in  the  negative.  She explained  that                                                                    
access to Anchorage would be via Whitter, Valdez, or Homer.                                                                     
                                                                                                                                
Co-Chair Stedman added Haines to Ms. Sirokys list.                                                                              
                                                                                                                                
1:30:58 PM                                                                                                                    
                                                                                                                                
Senator  Wielechowski asked  how many  active duty  military                                                                    
personnel used the AMHS to travel to and from the state.                                                                        
                                                                                                                                
Mr. McLaren  relayed that  in 2018,  military travel  in and                                                                    
out  of  Bellingham,  WA, equaled  907  vehicles  and  1,194                                                                    
passengers.  He added  that military  travel in  and out  of                                                                    
Prince Rupert consisted of 80 vehicles and 108 passengers.                                                                      
                                                                                                                                
Co-Chair Stedman  asked whether the number  included members                                                                    
of the Coast Guard.                                                                                                             
                                                                                                                                
Mr. McLaren replied in the affirmative.                                                                                         
                                                                                                                                
1:32:08 PM                                                                                                                    
                                                                                                                                
Senator  Wielechowski asked  about  the  return journey  for                                                                    
military personnel and families.                                                                                                
                                                                                                                                
Mr. McLaren stated that the  breakdown of those traveling to                                                                    
Bellingham was  438 vehicles and  568 passengers;  travel to                                                                    
Prince Rupert was 69 passengers and 47 vehicles.                                                                                
                                                                                                                                
Senator  Wielechowski  asked about  the  time  of year  that                                                                    
military travel occurred.                                                                                                       
                                                                                                                                
Mr. McLaren offered to provide the information later.                                                                           
                                                                                                                                
Co-Chair Stedman added that it  would be illuminating to see                                                                    
how  changes  in the  AMHS  schedule  would impact  military                                                                    
travel.                                                                                                                         
                                                                                                                                
1:33:19 PM                                                                                                                    
                                                                                                                                
Mr.  McLaren addressed  Slide 6,  "FY  2020 Governor's  2/13                                                                    
Budget":                                                                                                                        
                                                                                                                                
     Published summer schedule remains intact through the                                                                     
     end of August                                                                                                            
                                                                                                                                
     September 1, 2019 through September 30, 2019, operate:                                                                   
          ?Matanuska and  Malaspina on their  Bellingham and                                                                    
          SE Alaska runs                                                                                                        
          ?Tazlina in Northern Lynn Canal                                                                                       
          ?Lituya from Ketchikan  Annette Bay                                                                                   
          ?No  service  to  Homer, Kodiak,  Aleutian  Chain,                                                                    
          Whittier, Cordova, Valdez,  Chenega Bay, Tatitlek,                                                                    
          Yakutat, Prince Rupert,  Angoon, Tenakee, Pelican,                                                                    
          Hoonah, and Gustavus                                                                                                  
          ?Vessels    in   Layup:    Chenega,   Fairweather,                                                                    
          Kennicott,  Columbia, Tustumena,  Aurora, LeConte,                                                                    
          and Hubbard                                                                                                           
                                                                                                                                
     October 1, 2019, through June 30, 2020:                                                                                  
          ?No Service                                                                                                           
           Vessels in Layup:  All vessels                                                                                       
                                                                                                                                
          This schedule provides 84.8  weeks of service with                                                                  
          a potential fare box recovery rate of 40 percent.                                                                   
                                                                                                                              
          UGF:  $21,825.8                                                                                                       
          DGF*:  $17,869.3 (Revenues)                                                                                           
          Motor Fuel Tax Fund:  $3,617.1                                                                                        
          CIP Receipts:  $1,893.7                                                                                               
          *Includes DOT&PF Support Services                                                                                     
                                                                                                                                
          Expenditure Authorization:  $45,205.9                                                                                 
          Generated Revenue:  $17,869.3                                                                                         
          Net Deficit Amount: ($27,336.6)                                                                                       
                                                                                                                                
1:35:12 PM                                                                                                                    
                                                                                                                                
Senator Bishop asked about the expenditure authorization as                                                                     
listed on the slide and asked about the cost of vessel                                                                          
layup.                                                                                                                          
                                                                                                                                
Mr. McLaren estimated that in the 9 months that the ships                                                                       
would be laid up the cost would be $1.5 million, per month.                                                                     
                                                                                                                                
1:35:53 PM                                                                                                                    
                                                                                                                                
Senator   Wielechowski   asked   whether  there   were   any                                                                    
provisions in  any of  the collective  bargaining agreements                                                                    
that  covered AMHS  employees that  required that  employees                                                                    
continue to get paid even if service had stopped.                                                                               
                                                                                                                                
Mr. McLaren stated there were  some provisions for contracts                                                                    
in the bid awards. He said  that currently the bids had been                                                                    
awarded through  summer 2019. The  bid cycle for  the winter                                                                    
had not  started yet, but if  ships were laid up  then crews                                                                    
would be needed to keep the vessels safe.                                                                                       
                                                                                                                                
1:36:46 PM                                                                                                                    
                                                                                                                                
Co-Chair  Stedman asked  about the  standard timing  for the                                                                    
opening of  the reservation  system for the  October through                                                                    
winter timeframe.                                                                                                               
                                                                                                                                
Mr.  McLaren   stated  that  AMHS  normally   published  the                                                                    
schedule  in  July  and  August  after  a  budget  had  been                                                                    
approved.                                                                                                                       
                                                                                                                                
Co-Chair  Stedman  asked  whether reservations  for  October                                                                    
sailings, and through the winter, were taken in July.                                                                           
                                                                                                                                
Mr.  McLaren  stated  that   the  winter  schedule  (October                                                                    
through  April)  was  published   in  July  and  August  for                                                                    
booking.                                                                                                                        
                                                                                                                                
1:37:53 PM                                                                                                                    
                                                                                                                                
Senator  Micciche  asked whether  there  would  be no  state                                                                    
funded way  for people  from Juneau to  get vehicles  to and                                                                    
from   Juneau  to   the  road   system;   Juneau  would   be                                                                    
disconnected for 9 months.                                                                                                      
                                                                                                                                
Mr. McLaren answered in the affirmative.                                                                                        
                                                                                                                                
1:38:35 PM                                                                                                                    
                                                                                                                                
Ms. Siroky  thought it was  important to recognize  that the                                                                    
scenario on  Slide 6 was built  in order to ensure  that the                                                                    
commitment  had  been  met  for  travelers  who  had  booked                                                                    
sailings for summer 2019.                                                                                                       
                                                                                                                                
1:39:09 PM                                                                                                                    
                                                                                                                                
Senator  Wielechowski asked  whether the  ferry was  used by                                                                    
private businesses and if there  could be an economic impact                                                                    
as a result of the truncated sailing schedule.                                                                                  
Mr. McLaren  affirmed that many businesses  used the system,                                                                    
and 4  percent of  ferry traffic was  commercial. Commercial                                                                    
traffic  included   groceries  and  building   supplies  for                                                                    
smaller communities.                                                                                                            
                                                                                                                                
Senator Wielechowski  asked how  businesses would  ship good                                                                    
and products from  October through June if  the ferries were                                                                    
not operating.                                                                                                                  
                                                                                                                                
Ms. Siroky  stated that there  were barge lines  and freight                                                                    
services that  carried small amounts  of goods  and services                                                                    
throughout Southeast Alaska.                                                                                                    
                                                                                                                                
Senator Wielechowski  asked whether the other  services were                                                                    
comparable in  cost and  ran on the  same timetables  as the                                                                    
AMHS.                                                                                                                           
                                                                                                                                
Ms. Siroky  said that she was  not aware of the  barge lines                                                                    
scheduling. She  recalled that the barge  sailed weekly from                                                                    
Belling ham.  She expected that  the cost of  moving freight                                                                    
and  vehicles on  with  a commercial  outfit  would be  more                                                                    
expensive than the AMHS.                                                                                                        
                                                                                                                                
1:41:11 PM                                                                                                                    
                                                                                                                                
Senator Bishop recalled that in  years past there had been a                                                                    
discussion about forward-funding for  the system in order to                                                                    
give certainty for the public.                                                                                                  
                                                                                                                                
1:41:42 PM                                                                                                                    
                                                                                                                                
Co-Chair  Stedman  asked about  the  net  deficit under  the                                                                    
governors   proposed  budget,  which was  approximately  $27                                                                    
million, and would need to  be backfilled from the treasury.                                                                    
He noted that the cost of  mooring and tending ships laid up                                                                    
in port was included in that deficit.                                                                                           
                                                                                                                                
Mr. McLaren replied in the affirmative.                                                                                         
                                                                                                                                
1:42:21 PM                                                                                                                    
                                                                                                                                
Co-Chair  von  Imhof  asked  whether  the  $27  million  net                                                                    
deficit  amount  was  listed   in  the  governor's  proposed                                                                    
budget.                                                                                                                         
                                                                                                                                
Mr.  McLaren stated  that the  total budget  of $45  million                                                                    
included the cost. The department  had been asked to provide                                                                    
scenarios  that honored  the summer  schedule. He  said that                                                                    
the  department  had  looked   at  how  much  service  could                                                                    
continue  to be  provided, while  making funds  available to                                                                    
keep the state assets safe through the winter.                                                                                  
                                                                                                                                
Co-Chair  von Imhof  surmised that  the governor  was asking                                                                    
the legislature to  find the $27 million  necessary to cover                                                                    
the costs.                                                                                                                      
                                                                                                                                
Mr. McLaren stated  that the $27 million was  the total cost                                                                    
of the budget  of $45 million, minus the  revenue that could                                                                    
be  generated.  The $27  million  would  essentially be  the                                                                    
state subsidy for the schedule on Slide 6.                                                                                      
                                                                                                                                
1:44:34 PM                                                                                                                    
                                                                                                                                
Senator Wielechowski  had heard  different data on  how many                                                                    
jobs would  be lost through  proposed budget cuts.  He asked                                                                    
how  many  AMHS jobs  would  be  lost under  the  governors                                                                     
proposal.                                                                                                                       
                                                                                                                                
Ms. Siroky estimated that there  would be 300 positions lost                                                                    
if the  proposed budget was implemented.  She qualified that                                                                    
the  number did  not include  economic impacts  to ports  in                                                                    
communities  or  to Vigor,  the  company  in Ketchikan  that                                                                    
provided annual vessel maintenance.                                                                                             
                                                                                                                                
1:45:51 PM                                                                                                                    
                                                                                                                                
Co-Chair  Stedman  noted  that   Vigor  operated  the  state                                                                    
shipyard in Ketchikan and the AMHS was the anchor tenant.                                                                       
                                                                                                                                
1:46:20 PM                                                                                                                    
                                                                                                                                
Mr. McLaren showed Slide 7, "Outsourcing Service":                                                                              
                                                                                                                                
     Per  the  Collective  Bargaining  Agreements  with  the                                                                  
     vessel unions, service to the  following ports could be                                                                  
     outsourced  by the  State with  service to/from  Sitka,                                                                  
     Juneau and Petersburg:                                                                                                   
                                                                                                                                
     ?Angoon                                                                                                                    
     ?Gustavus                                                                                                                  
     ?Kake                                                                                                                      
     ?Hoonah                                                                                                                    
     ?Tenakee                                                                                                                   
     ?Pelican                                                                                                                   
Mr.  McLaren relayed  that  he  had been  asked  to look  at                                                                    
possibilities   for    outsourcing   service    to   certain                                                                    
communities.                                                                                                                    
                                                                                                                                
1:47:08 PM                                                                                                                    
                                                                                                                                
Co-Chair Stedman noted  that Angoon had no  barge service or                                                                    
airport. He stressed that all  communities were not equal in                                                                    
their ability  to procure goods  and services. He  asked Mr.                                                                    
McLaren  to elaborate  as  to why  the  specific ports  were                                                                    
listed rather than all ports.                                                                                                   
                                                                                                                                
Ms.  Siroky  stated  that   the  department  had  negotiated                                                                    
outsourcing with the unions when  the M/V LeConte was out of                                                                    
service. The  communities listed  had been  primarily served                                                                    
by that  vessel and  the department  had not  approached the                                                                    
issue with many other communities.                                                                                              
                                                                                                                                
Co-Chair Stedman asked  about other ports of  call. He asked                                                                    
if they would receive any service without the AMHS.                                                                             
                                                                                                                                
Ms.  Siroky answered  in the  affirmative. It  would not  be                                                                    
possible to  outsource service  to Haines,  Skagway, Valdez,                                                                    
or Kodiak.                                                                                                                      
                                                                                                                                
Co-Chair Stedman  asked if there  was a termination  date on                                                                    
the arrangement, or if it would run in perpetuity.                                                                              
                                                                                                                                
Ms. Siroky  did not know that  there was an end  date to the                                                                    
specific outsourcing.                                                                                                           
                                                                                                                                
Mr. McLaren interjected that these  were the ports listed in                                                                    
the current collective bargaining agreements.                                                                                   
                                                                                                                                
1:49:31 PM                                                                                                                    
                                                                                                                                
Senator Bishop pointed out that  there was no guarantee that                                                                    
there would be an entity to outsource ferry service to.                                                                         
                                                                                                                                
1:49:50 PM                                                                                                                    
                                                                                                                                
Senator  Wielechowski asked  whether  there  was any  Public                                                                    
Employees' Retirement System (PERS)  liability that would be                                                                    
incurred as a result of outsourcing.                                                                                            
                                                                                                                                
Co-Chair Stedman  explained that  when entities  were merged                                                                    
or sold,  it could trigger  a pension liability.  He relayed                                                                    
the possibility that  if the AMHS were shut  down, the state                                                                    
could  incur  a  liability  to   the  employees  for  vested                                                                    
benefits that were not fully funded.                                                                                            
                                                                                                                                
Ms.  Siroky  stated  that  there   would  be  liability  for                                                                    
individuals vested in  PERS. The state had  a terminal leave                                                                    
bank for individuals that were  cashing out leave at the end                                                                    
of  state service.  The department  had  not calculated  the                                                                    
potential costs.                                                                                                                
                                                                                                                                
Co-Chair  Stedman  asked  whether the  department  would  be                                                                    
coming forward with a supplemental  request in the future to                                                                    
cover the liability.                                                                                                            
                                                                                                                                
Ms.  Siroky did  not know  the  answer to  the question  and                                                                    
suggested  that  Department  of  Administration  would  best                                                                    
answer questions about the liability.                                                                                           
                                                                                                                                
1:51:54 PM                                                                                                                    
                                                                                                                                
Senator Wielechowski  asked whether it would  be possible to                                                                    
get an estimate of PERS withdrawal liability.                                                                                   
                                                                                                                                
1:52:09 PM                                                                                                                    
                                                                                                                                
Co-Chair  Stedman  asked  about  the  potential  termination                                                                    
costs listed  on Slide  6. He  had found  it would  cost $77                                                                    
million  to cover  the supplemental  funds.  He stated  that                                                                    
here were  significant adjustments to make,  relative to the                                                                    
proposed budget, to keep the system viable.                                                                                     
                                                                                                                                
1:54:08 PM                                                                                                                    
                                                                                                                                
Senator Wielechowski  asked whether the  governors  proposed                                                                    
budget considered the expense of laying up vessels.                                                                             
                                                                                                                                
Mr. McLaren answered in the affirmative.                                                                                        
                                                                                                                                
Senator Wielechowski asked for the amount.                                                                                      
                                                                                                                                
Mr. McLaren  repeated that  it would  cost $1.5  million per                                                                    
year to store and maintain the vessels.                                                                                         
                                                                                                                                
1:55:03 PM                                                                                                                    
                                                                                                                                
Co-Chair Stedman  wanted to  look at  scenarios to  keep the                                                                    
system going.  He mentioned a  study that would  be complete                                                                    
in late fall 2019 that would provide alternatives to the                                                                        
system, but in the meantime, he wanted to focus on keeping                                                                      
the AMHS viable.                                                                                                                
                                                                                                                                
1:55:45 PM                                                                                                                    
                                                                                                                                
Mr. McLaren spoke to Slide 8, "Example Scenario 1 Potential                                                                     
Outsourced Service Schedule":                                                                                                   
                                                                                                                                
     ?Sitka Angoon Hoonah Juneau                                                                                                
     ?One day per week, every other week                                                                                        
                                                                                                                                
     ?Juneau Hoonah Angoon Sitka                                                                                                
     ?One day per week, every other week                                                                                        
                                                                                                                                
     ?Juneau Gustavus Juneau                                                                                                    
     ?One day per week, every other week                                                                                        
                                                                                                                                
     ?Pelican and Tenakee                                                                                                       
     ?One port call per month                                                                                                   
                                                                                                                                
1:56:43 PM                                                                                                                    
                                                                                                                                
Mr. McLaren referenced Slide 9, "FY2020 AMHS Example                                                                            
Scenario 1 - Add Oct-June Outsourcing Villages of SE                                                                            
Panhandle":                                                                                                                     
                                                                                                                                
     Published summer schedule remains intact through the                                                                     
     end of August                                                                                                            
                                                                                                                                
     September 1, 2019 through September 30, 2019, operate:                                                                   
     ?Matanuska and Malaspina on their Bellingham and SE                                                                        
     Alaska runs                                                                                                                
     ?Kennicott on the Bellingham Whittier Cross-gulf run                                                                       
     ?Tustumena on the Homer-Kodiak/Aleutian Chain run                                                                          
     ?Tazlina in Northern Lynn Canal                                                                                            
     ?Lituya from Ketchikan Annette Bay                                                                                         
     ?Outsourced Service to SE Villages three days, every                                                                       
     other week                                                                                                                 
      Vessels in Layup: Chenega, Fairweather, Columbia,                                                                       
     LeConte, Aurora, Hubbard                                                                                                 
                                                                                                                                
     October 1, 2019 through March 31, 2020, operate:                                                                         
     ?Matanuska on the Bellingham run                                                                                           
     ?Tustumena on the Homer Kodiak Island and Cordova -                                                                        
     Valdez                                                                                                                     
     ?Tazlina in Northern Lynn Canal                                                                                            
     ?Lituya from Ketchikan Annette Bay                                                                                         
     ?Outsourced Service  to SE Villages  three  days, every                                                                    
     other week                                                                                                                 
      No service to Prince Rupert or Whittier                                                                                 
      Vessels  in  Layup: Chenega,  Fairweather,  Kennicott,                                                                  
     Malaspina, LeConte, Columbia, Aurora, Hubbard                                                                            
                                                                                                                              
     April 1, 2020, through June 30, 2020, operate:                                                                           
     ?Matanuska and Malaspina on the Bellingham run                                                                             
     ?Kennicott on the Juneau Whittier Cross-gulf run                                                                           
     ?Tustumena  on the  Homer-Kodiak  Island  run with  one                                                                    
     Aleutian Chain run                                                                                                         
     ?Hubbard in Prince William Sound                                                                                           
     ?Tazlina in Northern Lynn Canal                                                                                            
     ?Lituya from Ketchikan Annette Bay                                                                                         
     ?Outsourced Service  to SE Villages  three  days, every                                                                    
     other week                                                                                                                 
     • No service to Prince Rupert                                                                                            
     ?Vessels  in  Layup:   Chenega,  Fairweather,  LeConte,                                                                  
     Columbia, Aurora                                                                                                         
                                                                                                                                
     This   schedule  provides   288.8  weeks   of  service,                                                                    
     including the outsourced service  with a potential fare                                                                    
     box recovery rate of 50%.                                                                                                  
          Note: There will be gaps in service while the                                                                         
          vessels undergo their required annual COI                                                                             
          overhauls.                                                                                                            
                                                                                                                                
     UGF:  $41,605.9                                                                                                            
     DGF*:  $47,358.9 (Revenues)                                                                                                
     Motor Fuel Tax Fund:  $3,617.1                                                                                             
     CIP Receipts:  $1,893.7                                                                                                    
     *Includes DOT&PF Support Services                                                                                          
                                                                                                                                
     Expenditure Authorization:  $94,475.6                                                                                      
     Generated Revenue:  $47,358.9                                                                                              
     Net Deficit Amount: ($47,116.7)                                                                                            
                                                                                                                                
1:59:02 PM                                                                                                                    
                                                                                                                                
Co-Chair Stedman queried the departments confidence in the                                                                      
projected numbers on the slide.                                                                                                 
                                                                                                                                
Mr.  McLaren  stated  he  was  confident  with  the  numbers                                                                    
reflected on the  slide. He explained that  the schedule had                                                                    
been  crafted to  provide some  service to  all communities,                                                                    
while  simultaneously focusing  on summer  routes and  ports                                                                    
that generated the most revenue.                                                                                                
                                                                                                                                
1:59:59 PM                                                                                                                    
                                                                                                                                
Senator  Bishop  asked  whether   the  numbers  on  Slide  9                                                                    
included the funds to outsource.                                                                                                
                                                                                                                                
Mr. McLaren affirmed  that the numbers included  the cost of                                                                    
the outsource and the revenue  off that service. He reminded                                                                    
that the numbers were estimates.                                                                                                
                                                                                                                                
Senator  Bishop wondered  about the  Inner Island  Ferry for                                                                    
Prince of Whales Island.                                                                                                        
                                                                                                                                
Ms. Siroky affirmed  that the Inner Island  Ferry received a                                                                    
subsidy of approximately $250,000 for its operation.                                                                            
                                                                                                                                
Co-Chair  Stedman  noted that  the  Inner  Island Ferry  had                                                                    
regularly submitted  their financials  to OMB for  review to                                                                    
be  sure  that  the  state  was getting  a  good  return  on                                                                    
investment.                                                                                                                     
                                                                                                                                
Co-Chair  Stedman noted  that  there was  a  deficit of  $47                                                                    
million shown on Slide 9.                                                                                                       
                                                                                                                                
2:01:46 PM                                                                                                                    
                                                                                                                                
Co-Chair von Imhof considered that  the previous year, there                                                                    
was $86  million UGF going to  AMHS, and slide 9  showed $41                                                                    
million UGF. She  thought that even with cutting  the UGF in                                                                    
half, it  would be  helpful to have  a table  that reflected                                                                    
ridership.                                                                                                                      
                                                                                                                                
Mr.  McLaren   stated  that   upcoming  slides   would  show                                                                    
operating weeks and a side by side comparison.                                                                                  
                                                                                                                                
Co-Chair  Stedman wanted  to know  the increment  going from                                                                    
status quo to Scenario 1 and Scenario 2.                                                                                        
                                                                                                                                
2:03:22 PM                                                                                                                    
                                                                                                                                
Mr.  McLaren  reviewed  Slide  10,  "  FY2020  AMHS  Example                                                                    
Scenario 2  Add Oct-June  AMHS Operating  to Villages  of SE                                                                    
Panhandle":                                                                                                                     
                                                                                                                                
     Published  summer schedule  remains intact  through the                                                                  
     end of August                                                                                                            
                                                                                                                              
     September 1, 2019 through September 30, 2019, operate:                                                                   
     ?Matanuska  and Malaspina  on their  Bellingham and  SE                                                                    
     Alaska runs                                                                                                                
     ?Kennicott on the Bellingham Whittier Cross-gulf run                                                                       
     ?Tustumena on the Homer-Kodiak/Aleutian Chain run                                                                          
     ?Tazlina in Northern Lynn Canal                                                                                            
     ?Lituya from Ketchikan Annette Bay                                                                                         
      No  service to  Angoon,  Tenakee, and  Pelican due  to                                                                  
     LeConte's required overhaul                                                                                              
      Vessels  in  Layup:  Chenega,  Fairweather,  Columbia,                                                                  
     Aurora, Hubbard                                                                                                          
                                                                                                                                
     October 1, 2019 through March 31, 2020, operate:                                                                         
     ?Matanuska on the Bellingham run                                                                                           
     ?Tustumena on  the Homer  Kodiak  Island and  Cordova -                                                                    
     Valdez                                                                                                                     
     ?Lituya from Ketchikan Annette Bay                                                                                         
     ?LeConte -Dayboat  service to  Northern Lynn  Canal, SE                                                                    
     Panhandle, and Sitka                                                                                                       
     ?No service to Prince Rupert or Whittier                                                                                   
     ?Vessels  in  Layup: Chenega,  Fairweather,  Kennicott,                                                                    
     Malaspina, Columbia, Aurora,  Tazlina, Hubbard April 1,                                                                    
     2020, through June 30, 2020, operate:                                                                                      
     ?Matanuska and Malaspina on the Bellingham run                                                                             
     ?Kennicott on the Juneau Whittier Cross-gulf run                                                                           
     ?Tustumena  on the  Homer-Kodiak  Island  run with  one                                                                    
     Aleutian Chain run                                                                                                         
     ?Hubbard in Prince William Sound                                                                                           
     ?Tazlina in Northern Lynn Canal                                                                                            
     ?Lituya from Ketchikan Annette Bay                                                                                         
    ?LeConte -Dayboat service to SE Villages and Sitka                                                                          
      No service to Prince Rupert                                                                                             
     ?Vessels  in  Layup:  Chenega,  Fairweather,  Columbia,                                                                  
     Aurora                                                                                                                   
                                                                                                                                
     This schedule  provides 283.9 weeks  of service  with a                                                                    
     potential fare box recovery rate of 50%.                                                                                   
          Note: There will be gaps in service while the                                                                         
          vessels undergo their required annual COI                                                                             
          overhauls.                                                                                                            
                                                                                                                                
     UGF:  $43,124.7                                                                                                            
     DGF*:  $48,120.5 (Revenues)                                                                                                
     Motor Fuel Tax Fund:  $3,617.1                                                                                             
     CIP Receipts:  $1,893.7                                                                                                    
     *Includes DOT&PF Support Services                                                                                          
                                                                                                                                
     Expenditure Authorization:  $96,756.0                                                                                      
     Generated Revenue:  $48,120.5                                                                                              
     Net Deficit Amount: ($48,635.5)                                                                                            
                                                                                                                                
2:04:43 PM                                                                                                                    
                                                                                                                                
Mr. McLaren spoke to Slide 11, "Scenario Comparison,":                                                                          
                                                                                                                                
FY 2020Governor 2/13 Budget                                                                                                 
                                                                                                                                
July through August: Operate current published schedule                                                                         
                                                                                                                                
September: No service in SW Alaska, Prince William Sound,                                                                       
Prince Rupert, and SE Alaska Villages                                                                                           
                                                                                                                                
October through March: No Service                                                                                               
                                                                                                                                
April through June: No Service                                                                                                  
                                                                                                                                
Service Weeks (incl. Outsourcing weeks): 84.8                                                                                   
                                                                                                                                
Fare Box Recovery: 40 percent                                                                                                   
                                                                                                                                
Funding Sources: $21,825.8 UGF, $17,869.3 DGF, $3,617.1 Mtr                                                                     
Fuel Tax, $1,893.7 CIP Rcpts, $45,205.9 Total                                                                                   
                                                                                                                                
Net Deficit Amount ($27,336.6)                                                                                                  
                                                                                                                                
FY 2020 Example Scenario 1 - Add Oct-June - Outsourcing                                                                     
Villages of SE Panhandle                                                                                                    
                                                                                                                                
July through August: Operate current published schedule                                                                         
                                                                                                                                
September: Some service to all ports                                                                                            
                                                                                                                                
October through March: Some service to all ports except                                                                         
Prince Rupert and Whittier                                                                                                      
                                                                                                                                
April through June: Some service to all ports except Prince                                                                     
Rupert                                                                                                                          
                                                                                                                                
Service Weeks (incl. Outsourcing weeks): 288.8                                                                                  
                                                                                                                                
Fare Box Recovery: 50 percent                                                                                                   
Funding Sources: $41,605.9 UGF,  $47,358.9 DGF, $3,617.1 Mtr                                                                    
Fuel Tax, $1,893.7 CIP Rcpts, $94,475.6 Total                                                                                   
                                                                                                                                
Net Deficit Amount ($47,116.7)                                                                                                  
                                                                                                                                
FY 2020 Example  Scenario 2 - Add Oct-June  - AMHS Operating                                                                
to Villages of SE Panhandle                                                                                                 
                                                                                                                              
July through August: Operate current published schedule                                                                         
                                                                                                                                
September: No  service to Angoon, Tenakee,  and Pelican (Due                                                                    
to LeContes required annual overhaul)                                                                                           
                                                                                                                                
October  through March:  Some  service to  all ports  except                                                                    
Prince Rupert and Whittier                                                                                                      
                                                                                                                                
April through June: Some service  to all ports except Prince                                                                    
Rupert                                                                                                                          
                                                                                                                                
Service Weeks (incl. Outsourcing weeks): 283.9                                                                                  
                                                                                                                                
Fare Box Recovery: 50 percent                                                                                                   
                                                                                                                                
Funding Sources: $43,124.7 UGF,  $48,120.5 DGF, $3,617.1 Mtr                                                                    
Fuel Tax, $1,893.7 CIP Rcpts, $96,756.0 Total                                                                                   
                                                                                                                                
Net Deficit Amount ($48,635.5)                                                                                                  
                                                                                                                                
2:07:14 PM                                                                                                                    
                                                                                                                                
Co-Chair  von Imhof  observed  that Scenario  1  had 5  more                                                                    
service weeks at the cost of $2 million less UGF.                                                                               
                                                                                                                                
Mr. McLaren agreed.  The difference of the two  was that the                                                                    
LeConte would be operating 7  days per week, the outsourcing                                                                    
service would be operating 6 days per month.                                                                                    
                                                                                                                                
Co-Chair  von Imhof  wanted to  see how  many service  weeks                                                                    
were currently in place, and the funding sources attached.                                                                      
                                                                                                                                
Mr.  McLaren stated  that the  FY 19  budget included  345.9                                                                    
service weeks at $86 million UGF.                                                                                               
                                                                                                                                
2:08:41 PM                                                                                                                    
                                                                                                                                
Mr.  McLaren discussed  Slide  12,  "Example Scenario  Route                                                                    
Comparison Summer  2019 - Southeast," which  showed two maps                                                                    
of Southeast Alaska that had identical schedules:                                                                               
                                                                                                                                
Scenarios 1 and 2                                                                                                           
                                                                                                                              
Columbia (weekly round-trip)                                                                                                  
Bellingham, Ketchikan, Wrangell,  Petersburg, Sitka, Juneau,                                                                    
Haines, Skagway                                                                                                                 
                                                                                                                                
Malaspina (weekly round-trip)                                                                                                 
Prince  Rupert,   Ketchikan,  Wrangell,   Petersburg,  Kake,                                                                    
Sitka, Juneau, Haines, Skagway                                                                                                  
Kennicott (two-week round-trip)                                                                                               
Bellingham,  Ketchikan, Juneau,  Yakutat, Whittier,  Chenega                                                                    
Bay, Homer, Kodiak, Seldovia                                                                                                    
                                                                                                                                
Tazlina (dayboat  6 operating days per week)                                                                                  
Juneau, Haines, Skagway                                                                                                         
                                                                                                                                
LeConte (dayboat  7 operating days per week)                                                                                  
Juneau, Angoon, Tenakee, Hoonah, Gustavus, Pelican, Angoon                                                                      
                                                                                                                                
Lituya (dayboat  5 operating days per week)                                                                                   
Ketchikan, Annette Bay                                                                                                          
                                                                                                                                
2:09:21 PM                                                                                                                    
                                                                                                                                
Mr. McLaren  highlighted Slide  13, "Example  Scenario Route                                                                    
Comparison  Summer  2019   -Southwest,"  which  offered  the                                                                    
following scenarios:                                                                                                            
                                                                                                                                
     Scenarios 1 and 2                                                                                                      
                                                                                                                              
     Kennicott (two-week round trip)                                                                                          
     Bellingham, Ketchikan, Juneau, Yakutat, Whittier,                                                                          
     Chenega Bay, Homer, Kodiak, Seldovia                                                                                       
                                                                                                                                
     Aurora (dayboat  7 operating days per week)                                                                              
     Whittier, Valdez, Cordova, Tatitlek                                                                                        
                                                                                                                                
     Tustumena (two-week round trip)                                                                                          
     Homer, Seldovia, Kodiak, Port Lions, Ouzinkie, Old                                                                         
     Harbor, Chignik, Sand Point, King Cove, Cold Bay,                                                                          
     False Pass, Akutan, Dutch Harbor                                                                                           
                                                                                                                                
2:09:33 PM                                                                                                                    
Mr. McLaren discussed Slide 14, "Example Scenario Route                                                                         
Comparison Winter 2019/2020 -Southeast," which showed the                                                                       
following scenarios:                                                                                                            
                                                                                                                                
     Scenario 1                                                                                                             
                                                                                                                                
     Malaspina (weekly round-trip)                                                                                            
     Bellingham, Ketchikan, Wrangell, Petersburg, Kake,                                                                         
     Sitka, Juneau, Haines, Skagway                                                                                             
                                                                                                                                
     Tazlina (dayboat  4 operating days per week)                                                                             
     Juneau, Haines, Skagway, Hoonah, Gustavus                                                                                  
                                                                                                                                
     Lituya (dayboat  5 operating days per week)                                                                              
     Ketchikan, Annette Bay                                                                                                     
                                                                                                                                
     Outsourced Service (6 trips per month)                                                                                   
     Sitka, Angoon, Tenakee, Hoonah, Pelican, Gustavus,                                                                         
     Juneau                                                                                                                     
                                                                                                                                
     Scenario 2                                                                                                             
                                                                                                                                
     Malaspina (weekly round-trip)                                                                                            
     Bellingham, Ketchikan, Wrangell, Petersburg, Kake,                                                                         
     Sitka, Juneau, Haines, Skagway                                                                                             
                                                                                                                                
     LeConte (dayboat  7 operating days per week)                                                                             
     Juneau, Haines, Skagway, Hoonah, Gustavus, Pelican,                                                                        
     Angoon, Tenakee, Sitka                                                                                                     
                                                                                                                                
     Lituya (dayboat  5 operating days per week)                                                                              
     Ketchikan, Annette Bay                                                                                                     
                                                                                                                                
     Outsourced Service (6 trips per month)                                                                                   
     Sitka, Angoon, Tenakee, Hoonah, Pelican, Gustavus,                                                                         
     Juneau                                                                                                                     
                                                                                                                                
2:11:02 PM                                                                                                                    
                                                                                                                                
Mr. McLaren turned to slide 15, "Example Scenario Route                                                                         
Comparison Winter 2019/2020 - Southwest," and noted that                                                                        
there was no difference between the two scenarios:                                                                              
                                                                                                                                
     Scenarios 1 and 2                                                                                                      
     Tustumena (Cordova and Valdez twice per month)                                                                             
     Homer, Seldovia, Kodiak, Port Lions, Ouzinkie, Old                                                                         
     Harbor, Valdez, Cordova                                                                                                    
2:11:43 PM                                                                                                                    
                                                                                                                                
Co-Chair  Stedman observed  that the  scenarios on  Slide 15                                                                    
showed service to Kodiak, Old Harbor, Cordova, and Valdez.                                                                      
                                                                                                                                
Mr. McLaren replied in the affirmative.                                                                                         
                                                                                                                                
Co-Chair Stedman asked about the  difference between the two                                                                    
scenarios.                                                                                                                      
                                                                                                                                
Mr. McLaren repeated that the scenarios were the same.                                                                          
                                                                                                                                
Co-Chair  Stedman asked  about  out  fisheries workers  that                                                                    
b=needed transportation further down the Aleutian Chain.                                                                        
                                                                                                                                
Mr.  McLaren  stated  that  the  next  slide  would  provide                                                                    
further clarity.  He noted  that the system  did not  run to                                                                    
that  area in  the  winter months  because  the weather  was                                                                    
extreme and dangerous for sailing.                                                                                              
                                                                                                                                
Co-Chair  Stedman rebutted  that the  request was  not being                                                                    
made to run  additional routes, only to  salvage the service                                                                    
that was already in place.                                                                                                      
                                                                                                                                
2:13:06 PM                                                                                                                    
                                                                                                                                
Mr.  McLaren  moved to  Slide  16,  "Example Scenario  Route                                                                    
Comparison  Summer   2020  -Southeast,"  which   showed  the                                                                    
following run scenarios:                                                                                                        
                                                                                                                                
     Scenario 1                                                                                                             
                                                                                                                              
     Matanuska (weekly round-trip)                                                                                            
     Bellingham, Ketchikan, Wrangell, Petersburg, Sitka,                                                                        
     Juneau, Haines, Skagway                                                                                                    
                                                                                                                                
     Malaspina (weekly round-trip)                                                                                            
     Bellingham, Ketchikan, Wrangell, Petersburg, Kake,                                                                         
     Sitka, Juneau, Haines, Skagway                                                                                             
                                                                                                                                
     Kennicott (twice per week)                                                                                               
     Juneau, Yakutat, Whittier                                                                                                  
     Tazlina (dayboat  6 operating days per week)                                                                             
     Juneau, Haines, Skagway, Hoonah, Gustavus                                                                                  
                                                                                                                                
     Lituya (dayboat  5 operating days per week_                                                                              
     Ketchikan, Annette Bay                                                                                                     
     Outsourced Service (6 trips per month)                                                                                   
     Sitka, Angoon, Tenakee, Hoonah, Pelican, Gustavus,                                                                         
     Juneau                                                                                                                     
                                                                                                                                
     Scenario 2                                                                                                             
                                                                                                                              
     Matanuska (weekly round-trip)                                                                                            
     Bellingham, Ketchikan, Wrangell, Petersburg, Sitka,                                                                        
     Juneau, Haines, Skagway                                                                                                    
                                                                                                                                
     Malaspina (weekly round-trip)                                                                                            
     Bellingham, Ketchikan, Wrangell, Petersburg, Sitka,                                                                        
     Juneau, Haines, Skagway                                                                                                    
                                                                                                                                
     Kennicott (twice per week)                                                                                               
     Juneau, Yakutat, Whittier, Chenega Bay                                                                                     
                                                                                                                              
     Tazlina (dayboat  6 operating days per week)                                                                             
     Juneau, Haines, Skagway,                                                                                                   
                                                                                                                                
     LeConte (dayboat - 7 operating days per week)                                                                            
     Juneau, Hoonah, Gustavus, Tenakee, Angoon, Pelican,                                                                        
     Sitka, Kake                                                                                                                
                                                                                                                                
     Lituya (dayboat  5 operating days per week)                                                                              
     Ketchikan, Annette Bay                                                                                                     
                                                                                                                                
Mr. McLaren noted  that the chosen routes  were high demand,                                                                    
high income routes.                                                                                                             
                                                                                                                                
Co-Chair  Stedman asked  to  keep in  mind  that the  Prince                                                                    
Rupert area  had a  rail system  and had  plans for  a large                                                                    
liquefied  natural  gas project  in  the  future that  would                                                                    
create significant  economic activity.  He thought  it would                                                                    
be nice  to have  a port  of call in  Prince Rupert  so that                                                                    
workers  and   businesspeople  could  have  access   to  the                                                                    
economic  development in  that  area. He  thought access  to                                                                    
Prince  Rupert and  the rail  would help  to move  fish from                                                                    
Southeast  Alaska.  He  did  not  want  lose  sight  of  the                                                                    
economic activity  coming to the  area. He added  that there                                                                    
was a  port there already  that the state was  struggling to                                                                    
rebuild.                                                                                                                        
                                                                                                                                
Ms.  Siroky  stated  that  all the  scenarios  all  had  the                                                                    
dramatic  change  of  not  serving  Prince  Rupert.  In  the                                                                    
departments attempt  to bring  forward a  revenue maximizing                                                                    
scenario,  the  choice had  been  made  to drop  service  to                                                                    
Prince Rupert. She said that  money was saved in the Capital                                                                    
Budget by  dropping service to  the area. She said  that the                                                                    
state had  had some recent  issues with operating  in Prince                                                                    
Rupert.                                                                                                                         
                                                                                                                                
Co-Chair Stedman  asked about the  buying of  American steel                                                                    
and how it related to building  out the port in the area. He                                                                    
wanted  to highlight  the forthcoming  economic activity  in                                                                    
the region  and the  possibility of that  activity providing                                                                    
jobs for Alaskans. He stressed  that it would be unfortunate                                                                    
for the  state to miss  out on the economic  opportunity and                                                                    
have the action of pinching pennies cost us dollars.                                                                            
                                                                                                                                
2:17:11 PM                                                                                                                    
                                                                                                                                
Co-Chair Stedman pointed out that  Angoon did not have barge                                                                    
service or an  airport. He thought that,  depending on which                                                                    
scenario  was run,  the community  could be  in a  difficult                                                                    
position.  He  stressed  that  the  marine  highway  carried                                                                    
hospital patients  from that community to  Sitka and Juneau;                                                                    
limiting marine travel could  negatively affect the cultural                                                                    
practices of smaller communities.                                                                                               
                                                                                                                                
2:17:56 PM                                                                                                                    
                                                                                                                                
Mr.  McLaren referenced  slide 17,  "Example Scenario  Route                                                                    
Comparison:  Summer  2020  - Southwest,"  which  showed  the                                                                    
Aleutian Chain  run. The slide  showed the  example scenario                                                                    
route comparison  for both Scenarios  1 and 2. He  said that                                                                    
the  Kennicott would  come up  from  Juneau and  then go  to                                                                    
Yakutat  and Whittier  and Chenega  Bay.  The Hubbard  would                                                                    
operate  in  Prince  William  Sound,  Cordova,  Valdez,  and                                                                    
Whitter.  The  Tustumena  would operate  between  Homer  and                                                                    
Kodiak  Island.  The  scenario   also  included  an  earlier                                                                    
Aleutian Chain run  to get fishing vessels  and equipment to                                                                    
those  islands early  in the  fishing season.  The scenarios                                                                    
                  th                                                                                                            
cut out on June 30   and a late run had been investigated to                                                                    
get fishing vessels home later in the fishing season.                                                                           
                                                                                                                                
2:19:12 PM                                                                                                                    
                                                                                                                                
Co-Chair Stedman  noted that under both  scenarios there was                                                                    
some service  out to  the Aleutian  Chain, Kodiak,  and into                                                                    
Prince   William   Sound,   with  modified   services   into                                                                    
Southeast. He  surmised that Prince Rupert  would be without                                                                    
service until the next budget cycle.                                                                                            
                                                                                                                                
Mr. McLaren answered in the affirmative.                                                                                        
                                                                                                                                
Co-Chair  Stedman warned  underestimating the  popularity of                                                                    
Alaskans  wanting to  go  to Prince  Rupert.  He noted  that                                                                    
boarding in  Prince Rupert  required going  through Canadian                                                                    
customs, which  could lead  to drug  smuggling intervention.                                                                    
There  were various  angles and  reasons why  the people  of                                                                    
Southeast liked going through Prince Rupert.                                                                                    
                                                                                                                                
2:20:23 PM                                                                                                                    
                                                                                                                                
Senator  Bishop  asked  whether  the  state  had  granted  a                                                                    
contract for the study.                                                                                                         
                                                                                                                                
Ms.  Siroky  stated that  the  department  had announced  an                                                                    
"intent to award" and was in the 10-day protest period.                                                                         
                                                                                                                                
Senator Bishop asked  how much the outsourced  cost would be                                                                    
to get from Angoon to Juneau.                                                                                                   
                                                                                                                                
Mr.  McLaren  responded  that in  the  past  the  outsourced                                                                    
providers had honored the systems current tariffs.                                                                              
2:21:14 PM                                                                                                                    
                                                                                                                                
Senator  Wilson asked  whether there  were water  taxis that                                                                    
were traveling routes from Hoonah to Juneau.                                                                                    
                                                                                                                                
Mr. McLaren  did not know of  one from Hoonah to  Juneau. He                                                                    
thought there was one from Haines to Skagway.                                                                                   
                                                                                                                                
Ms. Siroky added that there  were some businesses that moved                                                                    
freight around but not a lot of passenger service.                                                                              
                                                                                                                                
Co-Chair   Stedman  stated   that   between  Coffman   Cove,                                                                    
Wrangell, and  Petersburg there had  been two  entities that                                                                    
had  tried  to  provide  taxi   service  but  had  not  been                                                                    
successful.  He thought  there  were  life-safety issues  to                                                                    
consider.                                                                                                                       
                                                                                                                                
Co-Chair  Stedman reiterated  that there  was a  significant                                                                    
amount  of  funding in  the  capital  budget that  had  been                                                                    
redirected to other  sources but could be moved  in a future                                                                    
budget if the marine highway were liquidated.                                                                                   
                                                                                                                                
2:24:14 PM                                                                                                                    
                                                                                                                                
Co-Chair von Imhof stated that  because the ferry system was                                                                    
so  capital and  operating budget  intensive, and  given the                                                                    
inner  play between  the  two budgets,  any  changes in  the                                                                    
funding of  the system would require  thoughtfully examining                                                                    
the budgets considering every aspect of the system.                                                                             
                                                                                                                                
Co-Chair Stedman  concluded that the legislature  would make                                                                    
an appropriation,  and the  administration would  manage the                                                                    
system. The  legislature would not  be selecting  vessels of                                                                    
routes but  would be appropriating  funds to be used  by the                                                                    
AMHS.                                                                                                                           
                                                                                                                                
2:25:45 PM                                                                                                                    
                                                                                                                                
Senator Olson asked whether there  had been discussion about                                                                    
air taxis picking up passenger traffic.                                                                                         
                                                                                                                                
Ms. Siroky replied in the negative.                                                                                             
                                                                                                                                
Co-Chair Stedman discussed housekeeping.                                                                                        
                                                                                                                                
ADJOURNMENT                                                                                                                   
2:27:32 PM                                                                                                                    
                                                                                                                                
The meeting was adjourned at 2:27 p.m.                                                                                          
                                                                                                                                
                                                                                                                                

Document Name Date/Time Subjects
041019 2019 SFIN - AMHS - 04.10.19 - FINAL.pdf SFIN 4/10/2019 1:00:00 PM
AMHS
041919 AMHS-USCG Operating Vessel Crew.pdf SFIN 4/10/2019 1:00:00 PM
AMHS