Legislature(2025 - 2026)BUTROVICH 205

05/05/2025 03:30 PM Senate RESOURCES

Note: the audio and video recordings are distinct records and are obtained from different sources. As such there may be key differences between the two. The audio recordings are captured by our records offices as the official record of the meeting and will have more accurate timestamps. Use the icons to switch between them.

Download Mp3. <- Right click and save file as

* first hearing in first committee of referral
+ teleconferenced
= bill was previously heard/scheduled
+= SB 32 ALLOWED COSTS IN ELECTRIC COOP RATES TELECONFERENCED
Heard & Held
-- Public Testimony --
+= SB 180 LNG IMPORT FACILITIES TELECONFERENCED
Heard & Held
-- Public Testimony --
Bills Previously Heard/Scheduled
**Streamed live on AKL.tv**
          SB  32-ALLOWED COSTS IN ELECTRIC COOP RATES                                                                       
                                                                                                                                
3:31:57 PM                                                                                                                    
CHAIR GIESSEL announced the consideration of SENATE BILL NO. 32                                                                 
"An Act relating to costs incurred by certain electric utilities                                                                
for renewable energy and battery energy storage."                                                                               
                                                                                                                                
3:32:06 PM                                                                                                                    
SENATOR HUGHES joined the meeting.                                                                                              
                                                                                                                                
3:32:07 PM                                                                                                                    
CHAIR GIESSEL, speaking as sponsor of SB 32, paraphrased from                                                                   
the sponsor statement:                                                                                                          
                                                                                                                                
[Original punctuation provided.]                                                                                                
                                                                                                                                
                   Senate Bill 32 (version N)                                                                                 
                       Sponsor Statement                                                                                      
                                                                                                                              
     "An Act relating to costs incurred by certain electric                                                                     
       utilities for renewable energy and battery energy                                                                        
                           storage."                                                                                            
                                                                                                                                
     This bill  seeks to remove barriers  to small renewable                                                                    
     energy and  battery storage  projects in  the Railbelt,                                                                    
     which will benefit Alaskans.                                                                                               
                                                                                                                                
     Alaska's  electric  cooperatives   organized  under  AS                                                                    
     10.25  that  participate  in the  Railbelt  Reliability                                                                    
     Council  certified  by  the  Regulatory  Commission  of                                                                    
     Alaska (RCA) are rate-regulated.                                                                                           
                                                                                                                                
     RRC       Railbelt  Reliability   Council,   integrated                                                                    
     planning process                                                                                                           
                                                                                                                                
     RTO  Railbelt Transmission Organization                                                                                    
                                                                                                                                
     This  legislation mirrors  the  approach  used by  many                                                                    
     electric   cooperatives  in   the  U.S.,   focusing  on                                                                    
     renewable  energy projects  and battery  energy storage                                                                    
     projects.                                                                                                                  
                                                                                                                                
CHAIR  GIESSEL   explained  that  the  legislature   created  the                                                               
Railbelt Reliability  Council (RRC) in 2024.  RRC does integrated                                                               
project planning for the railbelt  grid. She contrasted this with                                                               
the Railbelt  Transmission Organization (RTO), which  manages the                                                               
railbelt backbone transmission system.                                                                                          
                                                                                                                                
3:33:32 PM                                                                                                                    
CHAIR GIESSEL continued to paraphrase the sponsor statement for                                                                 
SB 32:                                                                                                                          
                                                                                                                                
[Original punctuation provided.]                                                                                                
                                                                                                                                
     This bill  would allow small renewable  energy projects                                                                    
     and  battery energy  storage projects  to advance  at a                                                                    
     faster  rate and  would  eliminate  the projects  under                                                                    
     five megawatts  from rate-regulation by  the Regulatory                                                                    
     Commission of Alaska,  thus freeing the RCA  to work on                                                                    
     larger, more pressing matters.                                                                                             
                                                                                                                                
     Projects five megawatts and larger  would still need to                                                                    
     go through the RCA for approval, as is currently done.                                                                     
                                                                                                                                
     SB  32  streamlines  the approval  process  for  adding                                                                    
     small  renewable  energy  and  battery  energy  storage                                                                    
     projects along the Railbelt.                                                                                               
                                                                                                                                
     This  will  help  diversify  generation  resources  and                                                                    
     gradually reduce  the reliance on fossil  fuel power by                                                                    
        electric utilities, leaving more locally sourced                                                                        
     natural gas available for other uses.                                                                                      
                                                                                                                                
     Under  this  bill, the  Houston  Solar  project is  8.5                                                                    
     megawatts  and [would  require]  rate  approval by  the                                                                    
     RCA.  Fire  Island Wind  is  17.6  megawatts and  would                                                                    
     still be required to seek rate approval from the RCA.                                                                      
                                                                                                                                
3:34:50 PM                                                                                                                    
CHAIR  GIESSEL commented  that  Regulatory  Commission of  Alaska                                                               
(RCA)  reviews  take  time.  She   added  that  the  reviews  are                                                               
extensive and costly. She emphasized  that the intention of SB 32                                                               
is  to  diversify  Alaska's   generation  resources  and  utilize                                                               
renewable energy sources when available.  She explained that this                                                               
legislation would exempt  up to three of  the 5-megawatt projects                                                               
from RCA approval  during a three-year timeframe.  She said these                                                               
changes  would  limit  the  effects  of  those  projects  on  the                                                               
transmission system.  She noted  that upcoming  invited testimony                                                               
would address this issue.                                                                                                       
                                                                                                                                
3:35:38 PM                                                                                                                    
SENATOR WIELECHOWSKI joined the meeting.                                                                                        
                                                                                                                                
3:35:54 PM                                                                                                                    
INTIMAYO  HARBISON, Staff,  Senator Cathy  Giessel, Alaska  State                                                               
Legislature,  Juneau, Alaska,  noted  that there  is a  committee                                                               
substitute (CS) for SB 32.                                                                                                      
                                                                                                                                
3:36:41 PM                                                                                                                    
CHAIR GIESSEL solicited a motion.                                                                                               
                                                                                                                                
3:36:52 PM                                                                                                                    
SENATOR  WIELECHOWSKI moved  to  adopt  the committee  substitute                                                               
(CS) for SB 32 work order 34-LS0307\I, as the working document.                                                                 
                                                                                                                                
3:37:09 PM                                                                                                                    
CHAIR GIESSEL objected for purposes of discussion.                                                                              
                                                                                                                                
3:37:14 PM                                                                                                                    
MR.  HARBISON  provided  a  brief  explanation  of  changes  from                                                               
version N  to version I of  SB 32. He directed  attention to CSSB
32, page  1, lines 9-10.  He explained  that the CS  would reduce                                                               
the size from  15,000 kilowatts to 5,000 kilowatts.  The CS would                                                               
also limit the number of projects  to no more than three projects                                                               
in a  three-year period. He  directed attention to CSSB  32, page                                                               
1, line  13 and  said the  CS changes  15,000 kilowatts  to 5,000                                                               
kilowatts. This  is the extent  of the changes between  version N                                                               
and version I.                                                                                                                  
                                                                                                                                
3:38:00 PM                                                                                                                    
SENATOR DUNBAR stated  that he preferred the  original version of                                                               
SB 32. He said he would  like to hear invited testimony regarding                                                               
the decision  to change 15,000  kilowatts to 5,000  kilowatts. He                                                               
opined that it  is unfortunate that the Houston  Solar Project in                                                               
the Matsu  Valley was too  large to meet the  5,000-kilowatt cap.                                                               
He stated that  he would have liked that project  to move forward                                                               
without requiring  RCA approval. He further  opined that reducing                                                               
the amount from  15,000 kilowatts to 5,000 kilowatts  is an over-                                                               
adjustment. He  suggested the possibility  of a  future amendment                                                               
to raise  the limit  to 10,000 kilowatts.  He emphasized  that he                                                               
supports the  original version of  SB 32,  but said he  would not                                                               
object to adopting the CS.                                                                                                      
                                                                                                                                
3:39:05 PM                                                                                                                    
CHAIR GIESSEL  said there are electric  transmission and economic                                                               
reasons for  the change from  15,000 to 5,000 kilowatts,  as well                                                               
as  for  limiting the  number  of  projects during  a  three-year                                                               
timeframe.  She indicated  that invited  testimony would  provide                                                               
further details.                                                                                                                
                                                                                                                                
3:39:27 PM                                                                                                                    
SENATOR CLAMAN  shared his understanding that  the three projects                                                               
per three-year period limits the  number of projects a particular                                                               
utility or  project manager can  have during that  timeframe; the                                                               
limit does not  apply to the total number  of projects regionally                                                               
or statewide. He asked whether this understanding is correct.                                                                   
                                                                                                                                
3:39:53 PM                                                                                                                    
CHAIR GIESSEL affirmed this understanding.                                                                                      
                                                                                                                                
3:40:04 PM                                                                                                                    
CHAIR  GIESSEL  removed  her  objection.  She  found  no  further                                                               
objection and  CSSB 32,  work order  34-LS0307\I, was  before the                                                               
committee.                                                                                                                      
                                                                                                                                
3:40:57 PM                                                                                                                    
GWEN  HOLDMANN, Chief  Scientist,  Alaska Center  for Energy  and                                                               
Power,  University   of  Alaska  Fairbanks,   Fairbanks,  Alaska,                                                               
introduced herself  and said she would  provide technical context                                                               
for CSSB 32, work order 34-LS0307\I.                                                                                            
                                                                                                                                
3:41:29 PM                                                                                                                    
MS. HOLDMANN advanced to slide 1 and provided a brief overview                                                                  
of CSSB 32. She pointed out the change in the project size                                                                      
threshold and the project count limit.                                                                                          
                                                                                                                                
3:41:50 PM                                                                                                                    
MS. HOLDMANN advanced to slide 2:                                                                                               
                                                                                                                                
[Original punctuation provided.]                                                                                                
                                                                                                                                
     What this bill does and does not do:                                                                                     
                                                                                                                                
        • Does not prohibit the construction of a project                                                                       
          <15 MW. This has  already been exempted (42.05.785                                                                    
              section    preapproval   for    large   energy                                                                    
          facilities). This  does not impact this  aspect of                                                                    
          "pre-approval."                                                                                                       
        • This bill addresses rate basing and pass-through                                                                      
          of costs from  IPPs. It allows the  utility to put                                                                    
          the entire costs of the  project (or PPA) into the                                                                    
          rate  base, without  being subject  to RCA  review                                                                    
          (only  the   coop  board  of   the  "constructing"                                                                    
          utility is the decision maker).                                                                                       
        • CS limits both the size and the number of                                                                             
          projects that can qualify.                                                                                            
                                                                                                                                
3:42:52 PM                                                                                                                    
MS. HOLDMANN advanced to slide 3:                                                                                               
                                                                                                                                
[Original punctuation provided.]                                                                                                
                                                                                                                                
     Why change the threshold from 15MW-> 5MW?                                                                                
                                                                                                                                
     The 5  MW threshold  reflects real  system constraints.                                                                    
     Projects larger  than 5 MW  are more likely  to connect                                                                    
     to  the   transmission  system  rather  than   a  local                                                                    
     distribution network,  making them  far more  likely to                                                                    
     impact other users and require regional coordination.                                                                      
                                                                                                                                
     There's   a    practical   inflection   pointtypically                                                                     
     somewhere between  5 and 10  MWwhere  a  project begins                                                                    
     injecting  more  power   than  the  local  distribution                                                                    
     system can safely or efficiently carry                                                                                     
                                                                                                                                
MS. HOLDMANN explained that the  Houston Solar Farm, a roughly 6-                                                               
megawatt project that was connected  to the distribution grid for                                                               
Matanuska Electric Association, is one  example of a project that                                                               
lies within that 510-megawatt inflection point.                                                                                 
                                                                                                                                
3:44:12 PM                                                                                                                    
MS. HOLDMANN said  that upcoming slides would  help to illustrate                                                               
this issue. She invited Steve Colt to present those slides.                                                                     
                                                                                                                                
                                                                                                                                
3:44:36 PM                                                                                                                    
STEVE  COLT, Research  Professor,  Alaska Center  for Energy  and                                                               
Power,  University   of  Alaska  Fairbanks,   Fairbanks,  Alaska,                                                               
advanced to slide 4, containing an image of an elephant:                                                                        
                                                                                                                                
[Original punctuation provided.]                                                                                                
                                                                                                                                
                       Thought experiment                                                                                     
                                                                                                                                
     Very expensive project (14 MW)                                                                                           
                                                                                                                                
     Current Scenario:                                                                                                          
        • Not prohibited under AS 42.05.785                                                                                     
        • Increased rates  could probably be  passed through                                                                    
          under SRF for a while                                                                                                 
        • But, the RCA might  not approve rate-basing of the                                                                    
          project at some point (e.g., general rate case).                                                                      
        • Another utility or other  parties within their own                                                                    
          service territory could challenge the rates.                                                                          
                                                                                                                                
     Original Language SB 32:                                                                                                   
        • Project   is  still   not   prohibited  under   AS                                                                    
          42.05.785                                                                                                             
        • The    additional   project    costs   would    be                                                                    
          automatically added to the rate base or passed                                                                        
          through (for purchased power)                                                                                         
        • They  could not  be  challenged by  others at  the                                                                    
          RCA.                                                                                                                  
        • Limits  other parties'  ability  to challenge  the                                                                    
          rate (especially another utility that is not                                                                          
          represented in the original decision).                                                                                
                                                                                                                                
MR.  COLT explained  that  currently, a  project  larger than  15                                                               
megawatts  would   be  subject   to  RCA  preapproval   under  AS                                                               
42.05.785. A project  that is 15 megawatts or  larger without RCA                                                               
approval is  prohibited. He briefly  described how  cost recovery                                                               
would impact rate payers and offered examples.                                                                                  
                                                                                                                                
3:50:51 PM                                                                                                                    
SENATOR  CLAMAN  shared  his   understanding  that  lowering  the                                                               
threshold  from  15 to  5  [megawatts]  is essentially  providing                                                               
consumer  protection, insofar  as  the increased  costs would  be                                                               
passed through via  rate increases. He asked  for confirmation of                                                               
this understanding.                                                                                                             
                                                                                                                                
3:51:31 PM                                                                                                                    
MR. COLT concurred. He said  the next slide would provide further                                                               
clarification.                                                                                                                  
                                                                                                                                
3:51:56 PM                                                                                                                    
MR. COLT  advanced to  slide 5,  containing an  image of  a small                                                               
elephant:                                                                                                                       
                                                                                                                                
[Original punctuation provided.]                                                                                                
                                                                                                                                
                  Thought experiment continued                                                                                
                                                                                                                              
     Very expensive project (4 MW)                                                                                              
                                                                                                                                
     Current Scenario:                                                                                                        
        • Not prohibited under AS 42.05.785                                                                                     
        • Increased rates  could probably be  passed through                                                                    
          under SRF for a while                                                                                                 
        • But, the RCA might  not approve rate-basing of the                                                                    
          project at some point (e.g., general rate case).                                                                      
        • Another utility or other  parties within their own                                                                    
          service territory could challenge the rates.                                                                          
                                                                                                                                
     CS for SB 32:                                                                                                            
        • Project   is  still   not   prohibited  under   AS                                                                    
          42.05.785                                                                                                             
        • The    additional   project    costs   would    be                                                                    
          automatically added to the rate base or passed                                                                        
          through (for purchased power)                                                                                         
        • They  could not  be  challenged by  others at  the                                                                    
          RCA.                                                                                                                  
        • Limits  other parties'  ability  to challenge  the                                                                    
          rate (especially another utility that is not                                                                          
          represented in the original decision).                                                                                
                                                                                                                                
MR.  COLT  explained that,  in  essence,  the co-op  board  would                                                               
determine  whether the  project is  prudent for  the purposes  of                                                               
going into  the rate  base. The  Regulatory Commission  of Alaska                                                               
(RCA) would not  be able to (directly) weigh in  on the project's                                                               
cost-effectiveness and  whether the project should  be allowed to                                                               
influence the rate base (whether in  whole or in part). He stated                                                               
that projects smaller than 5  megawatts depend on the co-op board                                                               
to  make  cost-effective  decisions;  therefore,  those  projects                                                               
could potentially  have fewer consumer protections.  He commented                                                               
that this  aligns with Senator  Claman's interpretation  that the                                                               
change to the  megawatt threshold would result  in added consumer                                                               
protections.  He asked  whether  this  sufficiently answers  that                                                               
question.                                                                                                                       
                                                                                                                                
SENATOR CLAMAN replied yes.                                                                                                     
                                                                                                                                
3:54:09 PM                                                                                                                    
MR. COLT  advanced to slide  6, containing  an image of  a small,                                                               
caged elephant:                                                                                                                 
                                                                                                                                
[Original punctuation provided.]                                                                                                
                                                                                                                                
     Thought experiment continued                                                                                             
                                                                                                                              
     Very expensive project (4 MW)                                                                                              
                                                                                                                                
     Current Scenario:                                                                                                        
        • Not prohibited under AS 42.05.785                                                                                     
        • Increased rates  could probably be  passed through                                                                    
          under SRF for a while                                                                                                 
        • But the  RCA might not approve  rate-basing of the                                                                    
          project at some point (e.g. general rate case).                                                                       
        • Another utility or other  parties within their own                                                                    
          service territory could challenge the rates.                                                                          
                                                                                                                                
     CS for SB32:                                                                                                             
        • Project   is  still   not   prohibited  under   AS                                                                    
          42.05.785                                                                                                             
        • The    additional   project    costs   would    be                                                                    
          automatically added to the rate base or passed                                                                        
          through (for purchased power)                                                                                         
        • They  could not  be  challenged by  others at  the                                                                    
          RCA.                                                                                                                  
        • Limits  other parties'  ability  to challenge  the                                                                    
          rate (especially another utility that is not                                                                          
          represented in the original decision).                                                                                
                                                                                                                                
3:54:11 PM                                                                                                                    
CHAIR GIESSEL asked for clarification  of the differences between                                                               
slide 5 and  slide 6. She noted  that the elephant on  slide 6 is                                                               
caged, while the elephant on slide 5 is not.                                                                                    
                                                                                                                                
3:54:44 PM                                                                                                                    
MR. COLT  said that the  cage on slide  6 is meant  to illustrate                                                               
that dropping the limit down to  5 megawatts not only reduces the                                                               
threshold  but also  limits the  project pool  to those  projects                                                               
which fit within the distribution system.                                                                                       
                                                                                                                                
3:55:32 PM                                                                                                                    
MS. HOLDMANN added that from  a technical standpoint, this limits                                                               
the  project   to  the  local  distribution   network.  From  the                                                               
standpoint of the  decision-maker, the co-op board  is the entity                                                               
making  decisions for  those  projects that  are  5 megawatts  or                                                               
lower. Therefore,  if project  costs escalate -  or if  the board                                                               
decides  the project  is worthwhile  despite  escalating costs  -                                                               
this is a local decision with  local impacts. She stated that the                                                               
Alaska Center  for Energy  and Power does  not want  to interfere                                                               
with a  board's ability to  move forward  with a project  of this                                                               
kind.                                                                                                                           
                                                                                                                                
3:56:32 PM                                                                                                                    
SENATOR MYERS noted  that the current scenarios  specified in the                                                               
presentation  included the  risk  that RCA  may  not approve  the                                                               
rate-basing of  a new project. He  asked what it means,  both for                                                               
the utility  and the consumer,  if the  RCA does not  approve the                                                               
rate-basing.                                                                                                                    
                                                                                                                                
3:57:01 PM                                                                                                                    
MS. HOLDMANN  said RCA has the  duty to ensure that  projects are                                                               
in  the  best  interest  of  consumers.  She  noted  cases  where                                                               
projects were  constructed that may or  may not have been  in the                                                               
best  interest of  consumers from  a rate  standpoint. The  RCA's                                                               
decision  regarding  any project  is  unknown,  which results  in                                                               
increased risk  for the utility (if  a project is built  that the                                                               
utility  cannot recover  rates from  in the  future). She  opined                                                               
that that is part of what SB 32 is addressing.                                                                                  
                                                                                                                                
3:58:11 PM                                                                                                                    
SENATOR  DUNBAR  asked for  clarification  about  whether the  6-                                                               
megawatt  Houston   Solar  Farm   did  or   did  not   alter  the                                                               
transmission system.                                                                                                            
                                                                                                                                
3:58:34 PM                                                                                                                    
MS. HOLDMANN explained  that there are many  technical factors to                                                               
consider, including  the robustness  of the  distribution system.                                                               
She  stated that  the Houston  Solar  Farm was  connected to  the                                                               
distribution system  - and was  at the system's upper  limit. She                                                               
stated that  the 5-megawatt threshold  is somewhat  arbitrary. An                                                               
alternative would  be to  consider any  project connected  to the                                                               
transmission versus the distribution  system. She reiterated that                                                               
the Houston  Solar Farm was  able to connect to  the distribution                                                               
grid.                                                                                                                           
                                                                                                                                
3:59:18 PM                                                                                                                    
SENATOR DUNBAR said that arbitrary  lines are often drawn because                                                               
of  their  simplicity  (and  sometimes   out  of  necessity).  He                                                               
surmised  that it  may  be better  to  consider the  transmission                                                               
versus distribution  system; however,  he acknowledged  that this                                                               
could introduce  a great deal  of complexity. He opined  that the                                                               
testimony  related to  the  Houston Solar  Farm,  along with  the                                                               
upcoming slides related  to economies of scale,  suggest that the                                                               
limit should fall somewhere above  5 megawatts. He suggested that                                                               
increasing the limit  would allow for larger  projects that could                                                               
meet  the economies  of scale  outlined in  the presentation.  He                                                               
wondered  if increasing  the  single-project limit  to  7 or  7.5                                                               
megawatts, with  a 3-year  limit of  15 megawatts  (regardless of                                                               
the total number of projects), would be a good alternative.                                                                     
                                                                                                                                
4:00:51 PM                                                                                                                    
MS. HOLDMANN  agreed that some  limits, including  the 5-megawatt                                                               
limit, are arbitrary.  She said that anything  over 7.5 megawatts                                                               
would almost  certainly be connected to  the transmission system;                                                               
however,  it  depends  on  the  project's  placement  within  the                                                               
overall  system.   She  said  she   is  not  prepared   to  speak                                                               
definitively on  this issue.  She mentioned  that CSSB  32 covers                                                               
both energy generation and battery  storage systems and suggested                                                               
that  considering  a  different  threshold  for  battery  storage                                                               
systems could  be appropriate, since those  systems interact with                                                               
the grid in a different way.                                                                                                    
                                                                                                                                
4:01:42 PM                                                                                                                    
SENATOR HUGHES asked whether the  local distribution systems vary                                                               
in capacity and could therefore  handle different thresholds. She                                                               
opined  that setting  the limit  around whether  a project  moves                                                               
beyond the local distribution system makes more sense.                                                                          
                                                                                                                                
4:02:48 PM                                                                                                                    
MS. HOLDMANN replied  that local distribution systems  do vary in                                                               
capacity; however, this  is related to infrastructure  as well as                                                               
the physical  electrical lines. Each  utility likely has  its own                                                               
unique  vulnerabilities  and  areas  with  stronger  distribution                                                               
nodes. She stated  that she is unable to speak  to any individual                                                               
utility.  She  reiterated  that   the  5-megawatt  threshold  was                                                               
arbitrary;  however, this  number  is also  related to  potential                                                               
economic impacts.  She referenced  the remaining three  slides in                                                               
her  presentation (slides  7-9) and  explained that  economies of                                                               
scale  are  limited   when  the  threshold  is   raised  above  5                                                               
megawatts.                                                                                                                      
                                                                                                                                
4:04:02 PM                                                                                                                    
CHAIR  GIESSEL  briefly  discussed   the  role  of  the  Railbelt                                                               
Reliability  Council (RRC)  in the  integrated planning  process.                                                               
She asked Ms. Holdmann to review this.                                                                                          
                                                                                                                                
4:04:26 PM                                                                                                                    
MS. HOLDMANN said the RRC  has two roles: setting reliability and                                                               
interconnection  standards and  resource planning.  She explained                                                               
that, in this case, any  projects greater than 15 megawatts would                                                               
be subject to the integrated  resource plan developed by the RRC.                                                               
She invited Mr. Colt to elaborate on this.                                                                                      
                                                                                                                                
4:05:00 PM                                                                                                                    
MR.  COLT added  that,  according to  Alaska  Statute, a  project                                                               
greater  than 15  megawatts must  be approved  in advance  by the                                                               
RCA. He  emphasized that  projects that  have not  received prior                                                               
approval  are  prohibited.  He  opined  that  this  is  a  "blunt                                                               
instrument" for projects greater than 15 megawatts.                                                                             
                                                                                                                                
4:06:20 PM                                                                                                                    
MS. HOLDMANN added that it may  be worth considering the point at                                                               
which  a project  of  a particular  size  may impact  neighboring                                                               
utility jurisdictions  or the transmission system.  She indicated                                                               
that it is  important to ensure that the arbiter  is clear in the                                                               
event of  disagreements between  different utilities.  She stated                                                               
that  gaps are  undesirable  and offered  examples to  illustrate                                                               
this point.                                                                                                                     
                                                                                                                                
4:07:22 PM                                                                                                                    
CHAIR GIESSEL said that there is  the potential to bypass RRC and                                                               
RCA by breaking  a large project into multiple  small pieces. She                                                               
acknowledged that the regulatory review  process (done by RCA) is                                                               
expensive  and lengthy;  however, this  process provides  greater                                                               
consumer  protection.  She  added  that RRC  is  responsible  for                                                               
generation planning. She asked for comment on this issue.                                                                       
                                                                                                                                
4:08:23 PM                                                                                                                    
MR. COLT briefly discussed gaps  in the supervisory structure. He                                                               
offered a hypothetical situation  involving a very costly project                                                               
that fell just  below the 15-megawatt threshold.  He stated that,                                                               
while  RCA  would  have  limited  authority  in  that  case,  the                                                               
utilities  involved  could  take  legal action.  He  offered  the                                                               
Bradley  Lake Hydroelectric  Project as  an example  of one  such                                                               
case.  The result  was  more  costly to  the  utilities than  RCA                                                               
involvement would have been.                                                                                                    
                                                                                                                                
4:10:21 PM                                                                                                                    
SENATOR  MYERS   stated  that  SB  32   applies  specifically  to                                                               
renewable  energy projects  and is  an attempt  to make  building                                                               
those projects  more accessible. He offered  several examples and                                                               
asked why,  if the intention  is to increase  experimentation and                                                               
get projects  on the grid more  quickly, this is not  extended to                                                               
all energy projects.                                                                                                            
                                                                                                                                
4:11:28 PM                                                                                                                    
MS. HOLDMANN deferred  the question and stated that  she does not                                                               
see a technical reason why SB 32 could not be expanded.                                                                         
                                                                                                                                
4:11:48 PM                                                                                                                    
CHAIR GIESSEL stated that her  intention is to expand the ability                                                               
for  renewable  projects  (particularly   solar  and  wind).  The                                                               
independent  power producers  and the  utilities are  considering                                                               
more renewable energy sources. She  opined that nuclear energy is                                                               
a  great  idea but  acknowledged  that  this is  not  technically                                                               
considered  a renewable  energy source.  She further  opined that                                                               
non-renewable  energy  sources  such  as  coal  and  natural  gas                                                               
require regulation.  She stated that  she would not object  to an                                                               
amendment adding nuclear energy to SB 32.                                                                                       
                                                                                                                                
4:13:27 PM                                                                                                                    
CHAIR GIESSEL opened public testimony on SB 32.                                                                                 
                                                                                                                                
4:13:55 PM                                                                                                                    
KEN  HUCKEBA, representing  self, Wasilla,  Alaska, testified  in                                                               
opposition to SB  32. He said he  is both a rate payer  and has a                                                               
history  in the  energy  industry.  He opined  that  SB  32 is  a                                                               
justification   for   small    infractions   to   become   larger                                                               
infractions. He  offered several examples to  illustrate this. He                                                               
said Alaska cannot  afford to have unreliable  energy sources. He                                                               
offered  to   supply  the  information   to  the   committee.  He                                                               
emphasized  that regulatory  oversight is  needed, regardless  of                                                               
project size. He indicated that  renewable energy sources are not                                                               
reliable  or affordable  and  SB 32  would  result in  ratepayers                                                               
paying   for   transmission   and   backup   infrastructure   for                                                               
"greenwashing  profiteers."  He   expressed  resentment  at  this                                                               
proposal and stated that he is opposed to SB 32.                                                                                
                                                                                                                                
4:16:29 PM                                                                                                                    
CASSIE ANDREWS,  representing self, Anchorage,  Alaska, testified                                                               
in opposition  to SB 32.  She asserted that the  changes proposed                                                               
by this  legislation are reckless  and dangerous.  She emphasized                                                               
the importance of  RCA oversight. She asserted  that, without RCA                                                               
oversight,   Alaskans  will   be   at  the   unchecked  will   of                                                               
environmental activists  pushing unreliable energy  projects. She                                                               
reiterated that  more oversight  is needed,  and RCA  must retain                                                               
the  authority  to  vet  projects before  they  are  thrust  onto                                                               
ratepayers.  She asserted  that  utility co-op  boards are  being                                                               
infiltrated by  radical green agenda  activists. She  stated that                                                               
SB 32 has no place in Alaska's energy future.                                                                                   
                                                                                                                                
4:17:32 PM                                                                                                                    
CHAIR GIESSEL closed public testimony on SB 32.                                                                                 
                                                                                                                                
4:17:46 PM                                                                                                                    
CHAIR GIESSEL held SB 32 in committee.                                                                                          

Document Name Date/Time Subjects
SB 180 Sponsor Statement.pdf SRES 5/5/2025 3:30:00 PM
SB 180
SB 180 Fiscal Note DCCED.pdf SRES 5/5/2025 3:30:00 PM
SB 180
SB 180 Sectional Analysis .pdf SRES 5/5/2025 3:30:00 PM
SB 180
SB 180 - RCA Notice if Utility Tariff Filing.pdf SRES 5/5/2025 3:30:00 PM
SB 180
CS v.I.pdf SRES 5/5/2025 3:30:00 PM
SB 32
SB 32 Sponsor Statement.pdf SRES 5/5/2025 3:30:00 PM
SB 32
SB 32 Sectional Analysis .pdf SRES 5/5/2025 3:30:00 PM
SB 32
SB 32 Holdmann Testimony.pdf SRES 5/5/2025 3:30:00 PM
SB 32
SB 32 Fiscal Note RCA.pdf SRES 5/5/2025 3:30:00 PM
SB 32