Legislature(2019 - 2020)BARNES 124
05/10/2019 01:00 PM House RESOURCES
Note: the audio
and video
recordings are distinct records and are obtained from different sources. As such there may be key differences between the two. The audio recordings are captured by our records offices as the official record of the meeting and will have more accurate timestamps. Use the icons to switch between them.
| Audio | Topic |
|---|---|
| Start | |
| SB91 | |
| HB116 | |
| Presentation(s): Understanding the Effects of Pfas (per- and Polyfluoroalkyl Substances) Contamination in Alaskan Municipalities | |
| Adjourn |
* first hearing in first committee of referral
+ teleconferenced
= bill was previously heard/scheduled
+ teleconferenced
= bill was previously heard/scheduled
| += | SB 91 | TELECONFERENCED | |
| + | TELECONFERENCED | ||
| += | HB 116 | TELECONFERENCED | |
| + | TELECONFERENCED |
SB 91-NUYAKUK RIVER: HYDROELECTRIC SITE
1:03:27 PM
CO-CHAIR TARR announced that the first order of business would
be CS FOR SENATE BILL NO. 91(FIN), "An Act relating to the
development and operation of a hydroelectric site at the Nuyakuk
River Falls; providing for the amendment of the management plan
for the Wood-Tikchik State Park; and providing for an effective
date."
CO-CHAIR TARR opened invited testimony on CSSB 91(FIN).
1:04:03 PM
ROBERT HIMSCHOOT, CEO/General Manager, Nushagak Cooperative,
provided a PowerPoint presentation titled "Nuyakuk
Hydroelectric, Hydropower for Bristol Bay." Turning to slide 2,
he said the [proposed] location offers some natural advantages
for hydroelectric production. He noted that the glacial moraine
that creates the lake systems of the Tikchik drains all five
lakes across that glacial moraine. He explained that the lake
is a natural sediment sink, that there is about 40 feet of head
across 2500 feet of river for a diversion project, and that the
2500 feet of river is in an oxbow configuration, which allows
for running a 1500-foot penstock.
MR. HIMSCHOOT moved to slide 3 and stated that since 1953 the
U.S. Geological Survey (USGS) has had a flow-monitoring gauge on
the river just above the proposed hydro site. He reported that
evaluation of these 60 years of flow data shows that 4.5
megawatts of power could still be made during the low three
months of the low three years, using less than 25 percent of the
flow; and during the summer considerably greater than 10
megawatts could be made. He further reported that the power
curve from this projected production matches the load dynamics
in Bristol Bay very well. Loads considerably peak in the summer
with salmon production, he explained, so being able to use a
consistent amount of the flow using the same dynamics would
produce power when it is needed the most as well as produce
enough power in the winter. He said the projection from this
curve is that the diesels can be turned off 24/7/365 in the
communities of Dillingham, Aleknagik, Koliganek, Stuyahok,
Ekwok, and Levelock. Other than during maintenance periods or
outages, he added, diesel power production would be completely
replaced by hydropower. He further pointed out that if the
actual study confirms the current projections, there is the
potential to also include Naknek, South Naknek, and King Salmon.
He specified that the diesel displacement projection for the
first subset of communities is 1.5 million gallons a year and if
the second subset is able to be included it will be 2.9 million
gallons a year.
MR. HIMSCHOOT displayed slide 4 and described how the power
plant facility would look on the river. He said 1,500 feet of
penstock would divert a portion of the flow across 2,500 feet of
river, so only 2,500 feet would be affected. He offered the
cooperative's belief that this project can be done with very
minimal impact to the viewshed and stated the studies will show
how much impact there would be to the natural environment. He
stated that while there is a considerable amount of data, modern
geographical information system (GIS) data would help quite a
bit in evaluation. The process requires that a considerable
amount of studying be done to be able to get an operating
license, he explained, and that is the point at which the
cooperative is right now. He said the cooperative has gone as
far as it can without getting in there and doing the physical
studies that will actually define whether the project is
feasible.
1:09:31 PM
REPRESENTATIVE TUCK observed the statement on slide 4, "Affected
water flow 3000 feet from the top of the falls to the bottom".
He inquired whether this is referring to a vertical or diagonal
drop of 3,000 feet.
MR. HIMSCHOOT replied that until there is the actual design [the
estimate is] 3,000 feet or 2,500 feet of longitudinal, not
vertical. That is the actual river flow, he clarified, and the
penstock, the pipeline that is put in there, is expected to be
closer to 1,500 feet.
1:10:13 PM
REPRESENTATIVE HOPKINS asked how many miles of transmission line
would need to be built to get power to the different villages.
MR. HIMSCHOOT responded it would be 130-150 [miles], depending
on whether Naknek, South Naknek, and King Salmon are able to
benefit from the project as well.
1:10:44 PM
REPRESENTATIVE TUCK asked how many people would be covered by
the project.
MR. HIMSCHOOT answered it would be between 3,500 and 4,500
people, depending on the scope of the project.
1:11:05 PM
REPRESENTATIVE HANNAN noted the bill just gives the Department
of Natural Resources (DNR) and the Alaska Department of Fish and
Game (ADF&G) the authority to amend the management plan for
Wood-Tikchik State Park so that the appropriate permitting can
go forward. She asked how much the project is going to cost and
how long it will take to construct.
MR. HIMSCHOOT replied that the Federal Energy Regulatory
Commission (FERC) is the permitting authority for anything over
five megawatts on an operating license. He stated this would
just allow the cooperative to get in there and follow the FERC
procedures and do the studies that will be necessary to that
process. The estimate right now, he continued, is $120-$150
million to construct the project. He said much of that would be
defined by the studies and if the studies show it is a viable
project, then the design that follows the studies if the
cooperative can acquire an operating permit.
REPRESENTATIVE HANNAN inquired how long the FERC process is
anticipated to take to get to a project that can be permitted.
MR. HIMSCHOOT responded that the studies themselves are expected
to take three years. He said the FERC process allows a three-
year window, which the cooperative is one year into right now.
As long as progress is being made, he continued, the FERC
process also allows a two-year extension. He related that the
cooperative expects it will need that extension and that
sometime between now and four years from now the study will be
completed. Once the studies are completed, he stated, there is
roughly one year for engineering and design and then hopefully a
two-year build process to bring this into production. So, he
added, if everything goes according to plan it is about a six-
year process from here.
1:13:38 PM
MR. HIMSCHOOT related that the Nushagak Cooperative started this
process in late 2017 and since then the cooperative has done
more than 70 meetings and presentations to build the social
license and support for the project that the cooperative knows
it will need in the region. Even though Nushagak Cooperative is
the entity that will be doing the studies here, he said, the
cooperative understands fully that this is a regional impact and
regional benefit and is doing everything it can to involve the
region. He pointed out that the substitute language seen in the
bill was part of that process. He explained that as the bill
entered the legislative process, the cooperative found some
local opposition to language in the bill. But, he continued,
the cooperative was able to bring everybody together through a
series of meetings and to come up with some additional language
that continues to build that needed local support and does not
materially affect the cooperative's ability to do the studies
that are needed.
MR. HIMSCHOOT addressed the [$20,000] fiscal note accompanying
the bill. He stated the cooperative has agreed to reimburse DNR
for its actual costs, estimated to be $20,000, to update the
management plan should the bill pass. That has several benefits
for the project as well as the bill, he added, which is why the
cooperative engaged in that process.
1:15:21 PM
CO-CHAIR TARR pointed out that before the committee is the
Senate-passed version, CSSB 91(FIN). She noted that the House
companion bill, HB 99, has the same original language as the
original Senate bill. She explained the original bill version
only added the Nuyakuk River Falls into existing statute as an
area where this activity could take place. She said more
specific restrictions would be added into statute by the amended
version, [CSSB 91 (FIN), page 1, lines 6-12], which read:
(e) The development and operation of a
hydroelectric site at the Nuyakuk River Falls is a
compatible use if the development and operation
(1) does not include a dam that full spans a
river;
(2) maintains at least 70 percent of the
daily upstream water flow of an affected river along
the natural course of the river; and
(3) after July 1, 2024, is licensed by the
Federal Energy Regulatory Commission.
1:17:00 PM
CO-CHAIR TARR opened public testimony on CSSB 91(FIN).
1:17:13 PM
CORY WARNOCK, Senior Licensing and Regulatory Consultant,
McMillen Jacobs Associates, testified he is representing the
Nushagak Cooperative regarding the regulatory side of things.
He related that in the past concern has been raised about this
bill somehow expediting the overall licensing process associated
with this project. Responding to Co-Chair Tarr, he provided
more details related to the FERC regulatory process. He said it
isn't a unique issue for park plans to be inconsistent with, or
incompatible with, the use of a hydroelectric project. What is
unique, he continued, is some of the concern that has been
raised. But, he stated, the reality is that the FERC regulatory
process is going to drive this overall licensing. All this bill
will allow, he advised, is for the Nushagak Cooperative to
actually conduct the requisite natural resource and engineering
studies required to determine whether this project is actually
feasible to construct and operate. The federal process will
trump anything else, he added, and if in four or five years the
natural resource and engineering studies show that this project
can't be built because of fish impacts, or flow impacts, or
other issues, Nushagak Cooperative has no intention of pushing
it through, nor could it. Things are at the infancy of this
overall federal process, he explained, and this is just the
light switch to allow that process to continue.
1:19:26 PM
CHRISTINE O'CONNOR, Executive Director, Alaska Telecom
Association (ATA), stated her personal support for CSSB 91(FIN)
and noted she is a former board member and a current customer of
Nushagak Cooperative. Speaking as a long-time former resident
of the region, she said the high cost of energy is a significant
economic drag on quality of life and therefore this project is
very exciting.
MS. O'CONNOR testified that ATA supports the bill because it has
a broadband component. She explained that, should the studies
prove it feasible to go forward, the infrastructure that would
eventually accompany the project would allow broadband fiber to
be deployed, which would also be a benefit to the region.
1:20:48 PM
CO-CHAIR TARR closed public testimony on CSSB 91(FIN) after
ascertaining that no one else wished to testify.
CO-CHAIR TARR requested Mr. Gease of the Division of Parks &
Outdoor Recreation to confirm that DNR anticipates entering into
a funding agreement with the project proponent under which DNR
would collect approximately $20,000 in receipts from the
proponent to cover costs incurred to revise the park management
plan and department regulations using the division's existing
receipt authority.
1:21:29 PM
RICKY GEASE, Director, Division of Parks & Outdoor Recreation,
Department of Natural Resources (DNR), confirmed Co-Chair Tarr's
statement is correct and accurate. He said the division would
follow that process moving forward.
1:21:51 PM
REPRESENTATIVE HANNAN noted that the original version of the
bill listed two lakes, but now [the bill as amended] only
considers a project that would be on the Nuyakuk River Falls.
She inquired whether Lake Elva and Grant Lake are both in Wood-
Tikchik State Park.
MR. GEASE offered his belief that hydro studies were done on
those lakes in the past, but that they proved to be not feasible
"and so this would be including this area to be a not
incompatible use with park purposes."
CO-CHAIR TARR stated, "They had previously tried and so the
original bill was just going to add the new location so that
they were all in that same section, but then I guess from the
community input, have further revised that."
REPRESENTATIVE HANNAN explained she is looking to see whether
those lakes were removed because of engineering infeasibility or
because of community response that a project was not wanted in
those lakes.
1:22:55 PM
MR. HIMSCHOOT responded that Nushagak Cooperative was granted
funding in 2009 to study Lake Elva and Grant Lake and the
studies were completed in 2012. There was potential for hydro
production, he said, but the amount that could be produced for
the cost of the project didn't allow the project to move forward
as it wasn't responsible financially to move it forward. At
that point, he continued, Nushagak Cooperative declared the two
projects not feasible, returned the remainder of the grant
funding to Alaska Energy Authority (AEA), and even though the
lakes remain in the statutory language the study results are in
the park management plan as far as feasibility is concerned.
1:24:16 PM
CO-CHAIR LINCOLN moved to report CSSB 91(FIN) out of committee
with individual recommendations and the accompanying fiscal
notes. There being no objection, CSSB 91(FIN) was reported out
of the House Resources Standing Committee.
| Document Name | Date/Time | Subjects |
|---|---|---|
| HB116 Sponsor Statement 4.15.19.pdf |
HFSH 4/16/2019 10:00:00 AM HFSH 4/25/2019 10:00:00 AM HRES 5/3/2019 1:00:00 PM HRES 5/10/2019 1:00:00 PM |
HB 116 |
| HB116 ver U 04.30.19.pdf |
HRES 5/3/2019 1:00:00 PM HRES 5/6/2019 1:00:00 PM HRES 5/10/2019 1:00:00 PM |
HB 116 |
| HB116 DNR Fiscal Note 04.30.19.pdf |
HRES 5/3/2019 1:00:00 PM HRES 5/6/2019 1:00:00 PM HRES 5/10/2019 1:00:00 PM |
HB 116 |
| HB116 ver U Sectional Analysis 04.30.19.pdf |
HRES 5/3/2019 1:00:00 PM HRES 5/6/2019 1:00:00 PM HRES 5/10/2019 1:00:00 PM |
HB 116 |
| HB116 Explanation of Changes ver A to ver U 04.30.19.pdf |
HRES 5/3/2019 1:00:00 PM HRES 5/6/2019 1:00:00 PM HRES 5/10/2019 1:00:00 PM |
HB 116 |
| HB116 Aquatic Farm Application Review Flow Chart 04.30.19.pdf |
HRES 5/3/2019 1:00:00 PM HRES 5/6/2019 1:00:00 PM HRES 5/10/2019 1:00:00 PM |
HB 116 |
| HB 116 - AFDF Letter of Support 2019-04-15.pdf |
HFSH 4/23/2019 10:00:00 AM HFSH 4/25/2019 10:00:00 AM HRES 5/10/2019 1:00:00 PM |
HB 116 |
| HB116 ASGA Letter of Support 04.15.19.pdf |
HFSH 4/23/2019 10:00:00 AM HFSH 4/25/2019 10:00:00 AM HRES 5/6/2019 1:00:00 PM HRES 5/10/2019 1:00:00 PM |
HB 116 |
| HB116 Supporting Document- Mariculture Plan.pdf |
HFSH 4/16/2019 10:00:00 AM HFSH 4/25/2019 10:00:00 AM HRES 5/3/2019 1:00:00 PM HRES 5/6/2019 1:00:00 PM HRES 5/10/2019 1:00:00 PM |
HB 116 |
| HB 116 Letter of Opposition-Hillstrand.pdf |
HFSH 4/25/2019 10:00:00 AM HRES 5/3/2019 1:00:00 PM HRES 5/10/2019 1:00:00 PM |
HB 116 |
| SB91 Sponsor Statement 3.21.19.pdf |
HRES 5/8/2019 1:00:00 PM HRES 5/10/2019 1:00:00 PM SRES 4/15/2019 3:30:00 PM |
SB 91 |
| SB91 Version A.pdf |
HRES 5/8/2019 1:00:00 PM HRES 5/10/2019 1:00:00 PM SRES 4/15/2019 3:30:00 PM |
SB 91 |
| SB91(FIN) Version S 5.6.19.PDF |
HRES 5/8/2019 1:00:00 PM HRES 5/10/2019 1:00:00 PM |
SB 91 |
| SB91 Fiscal Note DNR-PKS 3.29.19.pdf |
HRES 5/8/2019 1:00:00 PM HRES 5/10/2019 1:00:00 PM SRES 4/15/2019 3:30:00 PM |
SB 91 |
| SB 91 CS SB 91 (FIN) v. S Explanation.pdf |
HRES 5/8/2019 1:00:00 PM HRES 5/10/2019 1:00:00 PM SFIN 5/6/2019 9:00:00 AM |
SB 91 |
| SB91 BBNA Resolution 3.21.19.pdf |
HRES 5/8/2019 1:00:00 PM HRES 5/10/2019 1:00:00 PM SRES 4/15/2019 3:30:00 PM |
SB 91 |
| SB91 BBNC Letter 3.19.19.pdf |
HRES 5/8/2019 1:00:00 PM HRES 5/10/2019 1:00:00 PM SRES 4/15/2019 3:30:00 PM |
SB 91 |
| SB91 City of Dillingham Resolution 3.7.19.pdf |
HRES 5/8/2019 1:00:00 PM HRES 5/10/2019 1:00:00 PM SRES 4/15/2019 3:30:00 PM |
SB 91 |
| SB91 City of Aleknagik Resolution 3.19.19.pdf |
HRES 5/8/2019 1:00:00 PM HRES 5/10/2019 1:00:00 PM SRES 4/15/2019 3:30:00 PM |
SB 91 |
| SB91 CTC Resolution 3.12.19.pdf |
HRES 5/8/2019 1:00:00 PM HRES 5/10/2019 1:00:00 PM SRES 4/15/2019 3:30:00 PM |
SB 91 |
| SB91 NETC Resolution 11.15.17.pdf |
HRES 5/8/2019 1:00:00 PM HRES 5/10/2019 1:00:00 PM SRES 4/15/2019 3:30:00 PM |
SB 91 |
| SB91 Sectional Analysis 3.21.19.pdf |
HRES 5/8/2019 1:00:00 PM HRES 5/10/2019 1:00:00 PM SRES 4/15/2019 3:30:00 PM |
SB 91 |
| SB91 Nuyakuk Studies Cost Estimate.pdf |
HRES 5/8/2019 1:00:00 PM HRES 5/10/2019 1:00:00 PM SRES 4/15/2019 3:30:00 PM |
SB 91 |
| SB91 Nuyakuk Hydroelectric Update 2019.pdf |
HRES 5/8/2019 1:00:00 PM HRES 5/10/2019 1:00:00 PM SRES 4/15/2019 3:30:00 PM |
SB 91 |
| HB99_SB91_Nushagak Cooperative Presentation_Resources.pdf |
HRES 5/8/2019 1:00:00 PM HRES 5/10/2019 1:00:00 PM |
HB 99 SB 91 |
| City of Gustavus Supporting Documents.pdf |
HRES 5/10/2019 1:00:00 PM |
PFAS |
| HRES PFCs in the FNSB 5.10.19.pdf |
HRES 5/10/2019 1:00:00 PM |
SB 5 |
| SB91(FIN) Fiscal Note DNR-PKS 5.09.19.pdf |
HRES 5/10/2019 1:00:00 PM |
SB 91 |
| HRES DEC Presentation PFAS 5.10.19.pdf |
HRES 5/10/2019 1:00:00 PM |
PFAS |
| HB116 Supporting Document - DNR responses from 5.3.19 H RES meeting 5.10.19.pdf |
HRES 5/10/2019 1:00:00 PM |
HB 116 |
| City of Gustavus Supporting Documents - Rose Testimony 5.10.19.pdf |
HRES 5/10/2019 1:00:00 PM |
PFAS |